Difference between revisions of "HRRLPos Timeline Summary"
Jump to navigation
Jump to search
Line 41: | Line 41: | ||
|10/2011 || || Order Ion Pump Power supply and connectors | |10/2011 || || Order Ion Pump Power supply and connectors | ||
|- | |- | ||
− | |19/10/2011 || || Order 2 Flanges for quad7 beampipe from Duniway | + | |19/10/2011 || || [[Link https://wiki.iac.isu.edu/index.php/Instruments_and_Equipments#Beam_Pipe_for_Quad7 Order 2 Flanges for quad7 beampipe from Duniway]] |
|- | |- | ||
|20/10/2011 || || Order beampipe for quad7 and beampipe for 90 degree extension | |20/10/2011 || || Order beampipe for quad7 and beampipe for 90 degree extension |
Revision as of 18:10, 20 October 2011
Completion Date | IAC | Task |
9/10 | 2 weeks ($10k) | Chad builds and installs stands |
10/10 | 2 days ($1k) | IAC engineers move HRRL to new location |
10/10 | 2 weeks ($10 k) | Built beam pipe and flanges (Kevin?) |
10/10 | 2 weeks ($10k) | IAC engineers install beam line with magnets |
11/9/10 | RF conditioning | |
11/2910-12/15/10 | NRF experiment with moved HRRL | |
2/16/11 | OTR test with beam | |
3/3/11 | OTR test with beam | |
3/14/11-3/18/11 | Sadiq emittance measurements. Beam misalignment was discovered. It was discovered later during the 8/11 alignment that the beam line center was 1.5 cm below the center of the experimental cell port (hole through the wall). | |
7/2011 | 3 days ($1k) | Removed and reinstall Gun for alignment (Chad) |
3/11? | Sadiq and Khalid disassembles beam line for alignment | |
3/30/11 | Order Gate Valve (4 week lead time) | |
4/4/11 | Complete Beam Line CAD drawing (J. Ellis) | |
8/2011 | 1 week Mapped one Quad (Khalid, Sadiq) | |
8/2011 | 3 weeks Zero degree beam line aligned (Khalid, Sadiq) | |
8/2011 | $500 | 1 day IAC engineers assemble pump down zero degree beam line. Gate valve and OTR Flag installed |
10/2011 | 1 week Map 2nd Dipole (Khalid, Sadiq) | |
10/2011 | $1500 Order 2nd Ion Pump for HRRL File:HRRLIONPumpQUote102011.pdf | |
10/2011 | Order Ion Pump Power supply and connectors | |
19/10/2011 | Link https://wiki.iac.isu.edu/index.php/Instruments_and_Equipments#Beam_Pipe_for_Quad7 Order 2 Flanges for quad7 beampipe from Duniway | |
20/10/2011 | Order beampipe for quad7 and beampipe for 90 degree extension | |
1/25/2012 | Target Motor from Empire Magnetics | |
1/25/2012 | 1 week ($5k) | Target Chamber design (IAC engineer) |
1/25/2012 | Target Tungsten disks | |
2009-2012 | $30 k | 3 weeks of beam time |
IAC investment: $67.5k
Indirects from DOE : $90k
IAC personnel salary paid : $80k
Although not requested, magnet power supplies and a LabView control interface were installed by Chad. We were planning on using the old blue power supplies from the airport.