Difference between revisions of "HRRLPos Timeline Summary"
		
		
		
		
		
		Jump to navigation
		Jump to search
		
				
		
		
	
| Line 14: | Line 14: | ||
|-  | |-  | ||
|3/11?	||  ||Sadiq emittance measurements  | |3/11?	||  ||Sadiq emittance measurements  | ||
| + | |-  | ||
| + | |7/2011	        || 3 days ($1k) || Removed and reinstall Gun for alignment (Chad)  | ||
|-  | |-  | ||
|3/11?	||  ||Sadiq and Khalid disassembles beam line for alignment  | |3/11?	||  ||Sadiq and Khalid disassembles beam line for alignment  | ||
| Line 21: | Line 23: | ||
|4/4/11	        ||  ||Complete Beam Line CAD drawing (J. Ellis)  | |4/4/11	        ||  ||Complete Beam Line CAD drawing (J. Ellis)  | ||
|-  | |-  | ||
| − | |  | + | |8/2011	        || ||  1 week Mapped one Quad   (Khalid, Sadiq)  | 
| + | |-  | ||
| + | |8/2011	        || ||  3 weeks Zero degree beam line aligned (Khalid, Sadiq)  | ||
|-  | |-  | ||
| − | |  | + | |10/2011	        || ||  1 week Map 2nd Dipole  (Khalid, Sadiq)  | 
|-  | |-  | ||
|1/25/2012	|| || Target Motor  from Empire Magnetics  | |1/25/2012	|| || Target Motor  from Empire Magnetics  | ||
Revision as of 15:46, 17 October 2011
| Completion Date | IAC | Task | 
| 1/11? | IAC engineers move HRRL to new location | |
| 4/11/2011 | 2 weeks ($10 k) | Built beam pipe and flanges (Kevin?) | 
| 4/18/2011 | 2 weeks ($10k) | Chad builds and installs stands | 
| 1/11? | 2 weeks ($10k) | IAC engineers install beam line with magnets | 
| 2/11? | Hunt Runs experiment | |
| 3/11? | Sadiq emittance measurements | |
| 7/2011 | 3 days ($1k) | Removed and reinstall Gun for alignment (Chad) | 
| 3/11? | Sadiq and Khalid disassembles beam line for alignment | |
| 3/30/11 | Order Gate Valve (4 week lead time) | |
| 4/4/11 | Complete Beam Line CAD drawing (J. Ellis) | |
| 8/2011 | 1 week Mapped one Quad (Khalid, Sadiq) | |
| 8/2011 | 3 weeks Zero degree beam line aligned (Khalid, Sadiq) | |
| 10/2011 | 1 week Map 2nd Dipole (Khalid, Sadiq) | |
| 1/25/2012 | Target Motor from Empire Magnetics | |
| 1/25/2012 | 1 week ($5k) | Target Chamber design (IAC engineer) | 
| 1/25/2012 | Target Tungsten disks | |
| 2009-2012 | $30 k | 3 weeks of beam time | 
IAC investment: $66k
Indirects from DOE :
IAC personnel salary paid : $80k
Although not requested, magnet power supplies and a LabView control interface were installed by Chad. We were planning on using the old blue power supplies from the airport.