Difference between revisions of "HRRLPos Timeline Summary"
Jump to navigation
Jump to search
Line 29: | Line 29: | ||
Indirects from DOE : | Indirects from DOE : | ||
− | + | IAC personnel salary paid : $80k | |
Although not requested, magnet power supplies and a LabView control interface were installed by Chad. We were planning on using the old blue power supplies from the airport. | Although not requested, magnet power supplies and a LabView control interface were installed by Chad. We were planning on using the old blue power supplies from the airport. | ||
[[Positrons#HRRL_beam_Line_installation]] | [[Positrons#HRRL_beam_Line_installation]] |
Revision as of 03:04, 17 October 2011
Completion Date | IAC | Task |
1/11? | 2 weeks ($10k) | IAC engineers install beam line |
3/30/11 | Order Gate Valve (4 week lead time) | |
4/4/11 | Complete Beam Line CAD drawing (J. Ellis) | |
4/11/2011 | 2 weeks ($10 k) | Built beam pipe and flanges (Kevin?) |
4/18/2011 | 2 weeks ($10k) | Chad builds 4 stands |
7/2011 | 3 days ($1k) | Removed and reinstall Gun for alignment (Chad) |
8/2011 | Zero degree beam line aligned (Khalid, Sadiq) | |
1/25/2012 | Target Motor from Empire Magnetics | |
1/25/2012 | 1 week ($5k) | Target Chamber design (IAC engineer) |
1/25/2012 | Target Tungsten disks | |
2009-2012 | $30 k | 3 weeks of beam time |
IAC investment: $66k
Indirects from DOE : IAC personnel salary paid : $80k
Although not requested, magnet power supplies and a LabView control interface were installed by Chad. We were planning on using the old blue power supplies from the airport.