Difference between revisions of "HRRLPos Timeline Summary"

From New IAC Wiki
Jump to navigation Jump to search
Line 13: Line 13:
 
|7/2011         || 3 days ($1k) || Removed and reinstall Gun for alignment (Chad)
 
|7/2011         || 3 days ($1k) || Removed and reinstall Gun for alignment (Chad)
 
|-
 
|-
|8/2011         || Zero degree beam line aligned (Khalid, Sadiq)
+
|8/2011         || ||  Zero degree beam line aligned (Khalid, Sadiq)
 
|-
 
|-
|1/25/2012 || Target Motor  from Empire Magnetics
+
|1/25/2012 || || Target Motor  from Empire Magnetics
 
|-
 
|-
|1/25/2012 || Target Chamber
+
|1/25/2012 ||1 week ($5k) || Target Chamber design (IAC engineer)
 
|-
 
|-
|1/25/2012 || Target Tungsten disks
+
|1/25/2012 || || Target Tungsten disks
 
|}
 
|}
  
IAC investment: $21k
+
IAC investment: $26k
  
 
Indirects from DOE :
 
Indirects from DOE :
 +
 +
 +
Although not requested, magnet power supplies and a LabView control interface were installed by Chad.
  
 
[[Positrons#HRRL_beam_Line_installation]]
 
[[Positrons#HRRL_beam_Line_installation]]

Revision as of 02:59, 17 October 2011

Completion Date IAC Task
3/30/11 Order Gate Valve (4 week lead time)
4/4/11 Complete Beam Line CAD drawing (J. Ellis)
4/11/2011 2 weeks ($10 k) Built beam pipe and flanges (Kevin?)
4/18/2011 2 weeks ($10k) Chad builds 4 stands
7/2011 3 days ($1k) Removed and reinstall Gun for alignment (Chad)
8/2011 Zero degree beam line aligned (Khalid, Sadiq)
1/25/2012 Target Motor from Empire Magnetics
1/25/2012 1 week ($5k) Target Chamber design (IAC engineer)
1/25/2012 Target Tungsten disks

IAC investment: $26k

Indirects from DOE :


Although not requested, magnet power supplies and a LabView control interface were installed by Chad.