|7/2011	        || 3 days ($1k) || Removed and reinstall Gun for alignment (Chad)  | |7/2011	        || 3 days ($1k) || Removed and reinstall Gun for alignment (Chad)  | ||
|-  | |-  | ||
| − | |8/2011	        || Zero degree beam line aligned (Khalid, Sadiq)  | + | |8/2011	        || ||  Zero degree beam line aligned (Khalid, Sadiq)  | 
|-  | |-  | ||
| − | |1/25/2012	|| Target Motor  from Empire Magnetics  | + | |1/25/2012	|| || Target Motor  from Empire Magnetics  | 
|-  | |-  | ||
| − | |1/25/2012	|| Target Chamber  | + | |1/25/2012	||1 week ($5k) || Target Chamber design (IAC engineer)  | 
|-  | |-  | ||
| − | |1/25/2012	|| Target Tungsten disks  | + | |1/25/2012	|| || Target Tungsten disks  | 
|}  | |}  | ||
| − | IAC investment: $  | + | IAC investment: $26k  | 
Indirects from DOE :  | Indirects from DOE :  | ||
| + | |||
| + | |||
| + | Although not requested, magnet power supplies and a LabView control interface were installed by Chad.  | ||
[[Positrons#HRRL_beam_Line_installation]]  | [[Positrons#HRRL_beam_Line_installation]]  | ||
Revision as of 02:59, 17 October 2011
| Completion Date | IAC | Task | 
| 3/30/11 | Order Gate Valve (4 week lead time) | |
| 4/4/11 | Complete Beam Line CAD drawing (J. Ellis) | |
| 4/11/2011 | 2 weeks ($10 k) | Built beam pipe and flanges (Kevin?) | 
| 4/18/2011 | 2 weeks ($10k) | Chad builds 4 stands | 
| 7/2011 | 3 days ($1k) | Removed and reinstall Gun for alignment (Chad) | 
| 8/2011 | Zero degree beam line aligned (Khalid, Sadiq) | |
| 1/25/2012 | Target Motor from Empire Magnetics | |
| 1/25/2012 | 1 week ($5k) | Target Chamber design (IAC engineer) | 
| 1/25/2012 | Target Tungsten disks | 
IAC investment: $26k
Indirects from DOE :
Although not requested, magnet power supplies and a LabView control interface were installed by Chad.