Difference between revisions of "HRRLPos Timeline Summary"
Jump to navigation
Jump to search
m (Protected "HRRLPos Timeline Summary" ([edit=autoconfirmed] (indefinite) [move=autoconfirmed] (indefinite) [read=autoconfirmed] (indefinite))) |
|||
Line 1: | Line 1: | ||
{| border="1" |cellpadding="20" cellspacing="0 | {| border="1" |cellpadding="20" cellspacing="0 | ||
|- | |- | ||
− | | Completion Date || Task | + | | Completion Date || IAC ||Task |
|- | |- | ||
− | |3/30/11 || Order Gate Valve (4 week lead time) | + | |3/30/11 || ||Order Gate Valve (4 week lead time) |
|- | |- | ||
− | |4/4/11 || Complete Beam Line CAD drawing (J. Ellis) | + | |4/4/11 || ||Complete Beam Line CAD drawing (J. Ellis) |
|- | |- | ||
− | |4/11/2011 || Built beam pipe and flanges (Kevin?) | + | |4/11/2011 || 2 weeks ($10 k) ||Built beam pipe and flanges (Kevin?) |
|- | |- | ||
− | |4/18/2011 || Chad builds 4 stands | + | |4/18/2011 || 2 weeks ($10k) ||Chad builds 4 stands |
|- | |- | ||
− | |7/2011 || Removed Gun for alignment (Chad) | + | |7/2011 || 3 days ($1k) || Removed and reinstall Gun for alignment (Chad) |
|- | |- | ||
|8/2011 || Zero degree beam line aligned (Khalid, Sadiq) | |8/2011 || Zero degree beam line aligned (Khalid, Sadiq) | ||
Line 22: | Line 22: | ||
|} | |} | ||
+ | IAC investment: $21k | ||
+ | Indirects from DOE : | ||
[[Positrons#HRRL_beam_Line_installation]] | [[Positrons#HRRL_beam_Line_installation]] |
Revision as of 02:57, 17 October 2011
Completion Date | IAC | Task |
3/30/11 | Order Gate Valve (4 week lead time) | |
4/4/11 | Complete Beam Line CAD drawing (J. Ellis) | |
4/11/2011 | 2 weeks ($10 k) | Built beam pipe and flanges (Kevin?) |
4/18/2011 | 2 weeks ($10k) | Chad builds 4 stands |
7/2011 | 3 days ($1k) | Removed and reinstall Gun for alignment (Chad) |
8/2011 | Zero degree beam line aligned (Khalid, Sadiq) | |
1/25/2012 | Target Motor from Empire Magnetics | |
1/25/2012 | Target Chamber | |
1/25/2012 | Target Tungsten disks |
IAC investment: $21k
Indirects from DOE :