Completion Date Task
3/30/11 Order Gate Valve (4 week lead time)
4/4/11 Complete Beam Line CAD drawing (J. Ellis)
4/11/2011 Built beam pipe and flanges (Kevin?)
4/18/2011 Chad builds 4 stands
7/2011 Removed Gun for alignment (Chad)
8/2011 Zero degree beam line aligned (Khalid, Sadiq)
1/25/2012 Target Motor from Empire Magnetics
1/25/2012 Target Chamber
1/25/2012 Target Tungsten disks