| Completion Date | Task |
| 3/30/11 | Order Gate Valve (4 week lead time) |
| 4/4/11 | Complete Beam Line CAD drawing (J. Ellis) |
| 4/11/2011 | Built beam pipe and flanges (Kevin?) |
| 4/18/2011 | Chad builds 4 stands |
| 7/2011 | Removed Gun for alignment (Chad) |
| 8/2011 | Zero degree beam line aligned (Khalid, Sadiq) |
| 1/25/2012 | Target Motor from Empire Magnetics |
| 1/25/2012 | Target Chamber |
| 1/25/2012 | Target Tungsten disks |