Difference between revisions of "HRRLPos Timeline Summary"
Jump to navigation
Jump to search
| Line 5: | Line 5: | ||
|3/30/11 || Order Gate Valve (4 week lead time) | |3/30/11 || Order Gate Valve (4 week lead time) | ||
|- | |- | ||
| − | |4/4/11 || Complete Beam Line CAD drawing | + | |4/4/11 || Complete Beam Line CAD drawing |
|- | |- | ||
|4/11/2011 || Built beam pipe and flanges (Kevin?) | |4/11/2011 || Built beam pipe and flanges (Kevin?) | ||
|- | |- | ||
| − | |4/18/2011 || Chad builds | + | |4/18/2011 || Chad builds 4 stands |
|- | |- | ||
| − | |7/2011 || Removed Gun for alignment (Chad) | + | |7/2011 || Removed Gun for alignment (Chad) |
|- | |- | ||
| − | |8/2011 || Zero degree beam line aligned (Khalid, Sadiq) | + | |8/2011 || Zero degree beam line aligned (Khalid, Sadiq) |
|- | |- | ||
|1/25/2012 || Target Motor from Empire Magnetics | |1/25/2012 || Target Motor from Empire Magnetics | ||
| Line 21: | Line 21: | ||
|1/25/2012 || Target Tungsten disks | |1/25/2012 || Target Tungsten disks | ||
|} | |} | ||
| + | |||
| + | |||
[[Positrons#HRRL_beam_Line_installation]] | [[Positrons#HRRL_beam_Line_installation]] | ||
Revision as of 17:31, 16 October 2011
| Completion Date | Task |
| 3/30/11 | Order Gate Valve (4 week lead time) |
| 4/4/11 | Complete Beam Line CAD drawing |
| 4/11/2011 | Built beam pipe and flanges (Kevin?) |
| 4/18/2011 | Chad builds 4 stands |
| 7/2011 | Removed Gun for alignment (Chad) |
| 8/2011 | Zero degree beam line aligned (Khalid, Sadiq) |
| 1/25/2012 | Target Motor from Empire Magnetics |
| 1/25/2012 | Target Chamber |
| 1/25/2012 | Target Tungsten disks |