HRRL BeamLine 2011: Difference between revisions

From New IAC Wiki
Jump to navigation Jump to search
Foretony (talk | contribs)
Created page with '=Beam Line installation 2011= ==Timeline== {| border="1" |cellpadding="20" cellspacing="0 |- | Completion Date || Task |- |3/30/11 || Order Gate Valve (4 week lead time) |- …'
 
Foretony (talk | contribs)
Line 11: Line 11:
|4/4/11 ||  Complete Beam Line CAD drawing
|4/4/11 ||  Complete Beam Line CAD drawing
|-
|-
|4/11/2011 || Built beam pipe and flanges
|4/11/2011 || Built beam pipe and flanges (Kevin?)
|-
|-
|4/18/2011 ||  Complete Stands
|4/18/2011 ||  Complete Stands

Revision as of 15:59, 30 March 2011

Beam Line installation 2011

Timeline

Completion Date Task
3/30/11 Order Gate Valve (4 week lead time)
4/4/11 Complete Beam Line CAD drawing
4/11/2011 Built beam pipe and flanges (Kevin?)
4/18/2011 Complete Stands
4/25/2011 Built target chamber

Parts list

Positrons