Beam Line installation 2011

Timeline

Completion Date Task
3/30/11 Order Gate Valve (4 week lead time)
4/4/11 Complete Beam Line CAD drawing
4/11/2011 Built beam pipe and flanges (Kevin?)
4/18/2011 Complete Stands
4/25/2011 Built target chamber

Parts list