TF Management: Difference between revisions

From New IAC Wiki
Jump to navigation Jump to search
Oborn (talk | contribs)
New page: Timeline 7/30/08: Tony report's at Qweak collaboration meeting that GEM detector construction complete BUT the Charge collector Vendor has delayed delivery. 8/30/08: Latech and W&M comp...
 
Oborn (talk | contribs)
No edit summary
Line 1: Line 1:


Timeline
Timeline
Line 5: Line 4:
7/30/08: Tony report's at Qweak collaboration meeting that GEM detector construction complete BUT the Charge collector Vendor has delayed delivery.
7/30/08: Tony report's at Qweak collaboration meeting that GEM detector construction complete BUT the Charge collector Vendor has delayed delivery.
8/30/08: Latech and W&M components to the Collaborative MRI grant expire, Virginia Tech receives an extension
8/30/08: Latech and W&M components to the Collaborative MRI grant expire, Virginia Tech receives an extension
10/22/08: Charge collector arrives at ISU
10/23/08: Kathleen sends e-mail to Tony asking for requisition because MRI has expired and the GEM detector needs to be billed to the grant.
10/23/08: Kathleen sends e-mail to Tony asking for requisition because MRI has expired and the GEM detector needs to be billed to the grant.
10/30/08: Kathleen sends e-mail requesting that the chamber be sent so a property tag can be placed on it
10/30/08: Kathleen sends e-mail requesting that the chambers be sent so a property tag can be placed on it
11/6/08 : after several exchanges a final invoice version (#5?)  is sent to LaTech
11/19/08: Tony reports construction complete at Qweak collaboration meeting
11/24/08: 2 Qweak GEM detectors arrive at LaTex according to FedEx tracking.
11/24/08: 2 Qweak GEM detectors arrive at LaTex according to FedEx tracking.
1/19/08: Klaus tells Greg smith that the last R1 milestone is delayed from March, 09 until Oct. 09.

Revision as of 17:58, 24 January 2009

Timeline

7/30/08: Tony report's at Qweak collaboration meeting that GEM detector construction complete BUT the Charge collector Vendor has delayed delivery. 8/30/08: Latech and W&M components to the Collaborative MRI grant expire, Virginia Tech receives an extension 10/22/08: Charge collector arrives at ISU 10/23/08: Kathleen sends e-mail to Tony asking for requisition because MRI has expired and the GEM detector needs to be billed to the grant. 10/30/08: Kathleen sends e-mail requesting that the chambers be sent so a property tag can be placed on it 11/6/08 : after several exchanges a final invoice version (#5?) is sent to LaTech 11/19/08: Tony reports construction complete at Qweak collaboration meeting 11/24/08: 2 Qweak GEM detectors arrive at LaTex according to FedEx tracking.


1/19/08: Klaus tells Greg smith that the last R1 milestone is delayed from March, 09 until Oct. 09.