Day 1. December 3, 2007. MONDAY


Shift Personnel

Collaborator Shift
Amine 8-10 am , 2-4 pm
P. Bertin 8am - 5 pm
Syed 8 am - noon
T. Forest 10 am - 2pm

Task 1: Tune Beam

The first task will be to establish reproducable running conditions using the beam parameters given on the Main page.

This ask will also require that the FC and Pickup Coil be positioned and operating as well.

Task 2: Emmittance

Once stable beam operations are in place, we will insert two glass slides on the translator platform positioned 10 and 30 cm away from the Aluminum cooled exit window. Put beam on the windows and watch on the camera until the glass slides change color showing the beam envelope.

Next move the translator board to align the large glass plate at 50 cm away from the window and measure the beam profile


 Glass Slides at 10 cm, 30 cm, and 50 cm.  

Brett says the electron beam is focused to 1 mm in diameter before it strikes the exit window. After it passes throught the water-cooled exit window (Al 1mm - Water 1mm - Al 1mm), the beam swells to 6.0mm and at 30cm it the beam spot size is 2cm.

Here are two views of the exit window

Window1 Window2


 Beam spot size mapping in x and y with the Faraday Cup (FC) for z = 30cm from Window.  

We will move the table in or out depending on whether the beam spot size is greater or smaller than 2.0 cm. Translator table will be positioned at right position in z.



Task 3: Linearity tests of the pickup coil and FC.

We will just change the width of the pulse and compare the readings from the pickup coil to that of the FC. Note that change in 1mV from the pickup coil corresponds to 1mA change in the instantaneous beam current.

Pulse Width (us) pickup coil (mV) FC (mV)
0.08 PC FC

0.10

0.16

0.30
0.50
0.75
1.00
2.00


Here are Pictures of the Faraday Cup and the Pickup Coil

Faraday Cup Pickup Coil

Task 4: 5 hours of beamtime

Recall that we cannot exceed 10 K/h

  1. Irradiate broken PbF2 Crystal for 0.5 h and check the rate of the rise of temperature.

We will use a Fluke monitor with a camera to look at the temperature.

  1. Place Crystals 1, 2, 3, 4 on translator table.
    #Crystal 1:  0.5 hours
    # Crystal 2:  1 hour
    # Crystal 3:  1 hour
    # Crystal 4:  2 hours
  1. Transparency Test (~3 hours)
  2. Blue Light curing (24 hours)