8/1/12
Strung 35 Field wires on Sector 5 (now on SL2 - row 16).
Installed filters on Sector 6 chamber.
8/2/12
Strung 126 Field wires on Sector 5 (now on SL2 - row 33). Removed C1 pretensioner at row 25.
Strung 48 Sense wires on Sector 6 (now on SL2 - row 183).
Completed Tension Trend tests for both Sector 5 and 6 chambers.