7/2/12
Strung 84 Field wires on Sector 5 (now on SL2 - row 91). Removed pretensioner C3 at row 88.
Strung 41 Field wires on Sector 6 (SL1 Fields are now complete). Removed pretensioner C7 at row 228.
Began visual inspection of Sector 6 before rotation.
7/3/12
Strung 84 Field wires on Sector 5 (now on SL2 - row 103).
Completed visual inspection of Sector 6. Rotated chamber, leveled stringing machine, repositioned magnet and aligned chamber for stringing Sense wires in SL2.
7/5/12
Strung 42 Field wires on Sector 5 (now on SL2 - row 111). Removed pretensioner R3 at row 104.
Strung 25 Sense wires on Sector 6 (now on SL2 - row 12).
Completed weekly Tension Trend Tests for both Sector 5 and Sector 6.
7/9/12
Strung 84 Field wires on Sector 5 (now on SL2 - row 121).
Strung 36 Sense wires on Sector 6 (now on SL2 - row 24).