Difference between revisions of "201205 R1ProgressRep"

From New IAC Wiki
Jump to navigation Jump to search
Line 69: Line 69:
 
0.5 micron = 11,500 / cubic meter
 
0.5 micron = 11,500 / cubic meter
 
5.0 micron = 824 / cubic meter
 
5.0 micron = 824 / cubic meter
 +
 +
 +
=5/15/12=
 +
 +
Completed testing of all wires adjacent to wires that have been restrung. From now on, this task will be completed on the day that wires are restrung.
 +
 +
Replaced furnace filter.

Revision as of 15:22, 16 May 2012

5/1/12

Strung 84 Field wires on Chamber 6.

Strung 48 Guard wires on Chamber 5.


5/2/12

Strung 98 Field wires on Chamber 6.

Strung 35 Guard wires on Chamber 5.


5/3/12

Strung 84 Field wires on Chamber 6 (Now on row 181).

Strung 45 Guard wires on Chamber 5 (Now on row 123).


5/4/12

Strung 39 Guard wires on Chamber 5 (Now on row 162).

5/7/12

Strung 63 Field wires on Chamber 6 (Now on row 191).

5/8/12

Strung 56 Field wires on Chamber 6 (Now on row 200).

5/9/12

Strung 49 Field wires on Chamber 6 (Now on row 208).

Strung 13 Guard wires on Chamber 5 (Now on row 176).


5/10/12

Strung 63 Field wires on Chamber 6 (Now on row 217).

Strung 35 Guard wires in Chamber 5 (Now on row 211).


5/11/12

Strung 14 Field wires on Chamber 6 (Now on row 219).

Strung 23 Guard wires on Chamber 5 (Superlayer 2 complete).

Soldered and repaired 16 stringing chains.

Completed weekly trend test on Chamber 6.


5/14/12

Strung 63 Field wires on Chamber 6. (Superlayer 2 complete.)

Completed visual inspection of Chamber 6 Field wires.

Completed visual inspection of Chamber 5 Guard wires.

The railing on the upper floor was installed today. A particle count was run after completion and before stringing operations continued. The results were as follows: 0.5 micron = 11,500 / cubic meter 5.0 micron = 824 / cubic meter


5/15/12

Completed testing of all wires adjacent to wires that have been restrung. From now on, this task will be completed on the day that wires are restrung.

Replaced furnace filter.