Completed weekly trend test on Chamber 6. | Completed weekly trend test on Chamber 6. | ||
+ | |||
+ | |||
+ | =5/14/12= | ||
+ | |||
+ | Strung 63 Field wires on Chamber 6. (Superlayer 2 complete.) | ||
+ | |||
+ | Completed visual inspection of Chamber 6 Field wires. | ||
+ | |||
+ | Completed visual inspection of Chamber 5 Guard wires. | ||
+ | |||
+ | The railing on the upper floor was installed today. A particle count was run after completion and before stringing operations continued. The results were as follows: | ||
+ | 0.5 micron = 11,500 / cubic meter | ||
+ | 5.0 micron = 824 / cubic meter |
Revision as of 21:52, 14 May 2012
5/1/12
Strung 84 Field wires on Chamber 6.
Strung 48 Guard wires on Chamber 5.
5/2/12
Strung 98 Field wires on Chamber 6.
Strung 35 Guard wires on Chamber 5.
5/3/12
Strung 84 Field wires on Chamber 6 (Now on row 181).
Strung 45 Guard wires on Chamber 5 (Now on row 123).
5/4/12
Strung 39 Guard wires on Chamber 5 (Now on row 162).
5/7/12
Strung 63 Field wires on Chamber 6 (Now on row 191).
5/8/12
Strung 56 Field wires on Chamber 6 (Now on row 200).
5/9/12
Strung 49 Field wires on Chamber 6 (Now on row 208).
Strung 13 Guard wires on Chamber 5 (Now on row 176).
5/10/12
Strung 63 Field wires on Chamber 6 (Now on row 217).
Strung 35 Guard wires in Chamber 5 (Now on row 211).
5/11/12
Strung 14 Field wires on Chamber 6 (Now on row 219).
Strung 23 Guard wires on Chamber 5 (Superlayer 2 complete).
Soldered and repaired 16 stringing chains.
Completed weekly trend test on Chamber 6.
5/14/12
Strung 63 Field wires on Chamber 6. (Superlayer 2 complete.)
Completed visual inspection of Chamber 6 Field wires.
Completed visual inspection of Chamber 5 Guard wires.
The railing on the upper floor was installed today. A particle count was run after completion and before stringing operations continued. The results were as follows: 0.5 micron = 11,500 / cubic meter 5.0 micron = 824 / cubic meter