Difference between revisions of "HRRLPos Timeline Summary"
Jump to navigation
Jump to search
Line 14: | Line 14: | ||
|- | |- | ||
|3/11? || ||Sadiq emittance measurements | |3/11? || ||Sadiq emittance measurements | ||
+ | |- | ||
+ | |7/2011 || 3 days ($1k) || Removed and reinstall Gun for alignment (Chad) | ||
|- | |- | ||
|3/11? || ||Sadiq and Khalid disassembles beam line for alignment | |3/11? || ||Sadiq and Khalid disassembles beam line for alignment | ||
Line 21: | Line 23: | ||
|4/4/11 || ||Complete Beam Line CAD drawing (J. Ellis) | |4/4/11 || ||Complete Beam Line CAD drawing (J. Ellis) | ||
|- | |- | ||
− | | | + | |8/2011 || || 1 week Mapped one Quad (Khalid, Sadiq) |
+ | |- | ||
+ | |8/2011 || || 3 weeks Zero degree beam line aligned (Khalid, Sadiq) | ||
|- | |- | ||
− | | | + | |10/2011 || || 1 week Map 2nd Dipole (Khalid, Sadiq) |
|- | |- | ||
|1/25/2012 || || Target Motor from Empire Magnetics | |1/25/2012 || || Target Motor from Empire Magnetics |
Revision as of 15:46, 17 October 2011
Completion Date | IAC | Task |
1/11? | IAC engineers move HRRL to new location | |
4/11/2011 | 2 weeks ($10 k) | Built beam pipe and flanges (Kevin?) |
4/18/2011 | 2 weeks ($10k) | Chad builds and installs stands |
1/11? | 2 weeks ($10k) | IAC engineers install beam line with magnets |
2/11? | Hunt Runs experiment | |
3/11? | Sadiq emittance measurements | |
7/2011 | 3 days ($1k) | Removed and reinstall Gun for alignment (Chad) |
3/11? | Sadiq and Khalid disassembles beam line for alignment | |
3/30/11 | Order Gate Valve (4 week lead time) | |
4/4/11 | Complete Beam Line CAD drawing (J. Ellis) | |
8/2011 | 1 week Mapped one Quad (Khalid, Sadiq) | |
8/2011 | 3 weeks Zero degree beam line aligned (Khalid, Sadiq) | |
10/2011 | 1 week Map 2nd Dipole (Khalid, Sadiq) | |
1/25/2012 | Target Motor from Empire Magnetics | |
1/25/2012 | 1 week ($5k) | Target Chamber design (IAC engineer) |
1/25/2012 | Target Tungsten disks | |
2009-2012 | $30 k | 3 weeks of beam time |
IAC investment: $66k
Indirects from DOE :
IAC personnel salary paid : $80k
Although not requested, magnet power supplies and a LabView control interface were installed by Chad. We were planning on using the old blue power supplies from the airport.