Difference between revisions of "HRRLPos Timeline Summary"

From New IAC Wiki
Jump to navigation Jump to search
Line 3: Line 3:
 
| Completion Date || IAC ||Task
 
| Completion Date || IAC ||Task
 
|-
 
|-
|1/11? || 2 weeks ($10k) ||IAC engineers install beam line
+
|1/11? || ||IAC engineers move HRRL to new location
 
|-
 
|-
|3/11? ||  ||Hunt Runs experiment
+
|4/11/2011 || 2 weeks ($10 k) ||Built beam pipe and flanges (Kevin?)
 +
|-
 +
|4/18/2011 ||  2 weeks ($10k) ||Chad builds and installs  stands
 +
|-
 +
|1/11? || 2 weeks ($10k) ||IAC engineers install beam line with magnets
 +
|-
 +
|2/11? ||  ||Hunt Runs experiment
 +
|-
 +
|3/11? ||  ||Sadiq emittance measurements
 +
|-
 +
|3/11? ||  ||Sadiq and Khalid disassembles beam line for alignment
 
|-
 
|-
 
|3/30/11 ||  ||Order Gate Valve (4 week lead time)
 
|3/30/11 ||  ||Order Gate Valve (4 week lead time)
 
|-
 
|-
 
|4/4/11         ||  ||Complete Beam Line CAD drawing (J. Ellis)
 
|4/4/11         ||  ||Complete Beam Line CAD drawing (J. Ellis)
|-
 
|4/11/2011 || 2 weeks ($10 k) ||Built beam pipe and flanges (Kevin?)
 
|-
 
|4/18/2011 ||  2 weeks ($10k) ||Chad builds 4 stands
 
 
|-
 
|-
 
|7/2011         || 3 days ($1k) || Removed and reinstall Gun for alignment (Chad)
 
|7/2011         || 3 days ($1k) || Removed and reinstall Gun for alignment (Chad)

Revision as of 15:41, 17 October 2011

Completion Date IAC Task
1/11? IAC engineers move HRRL to new location
4/11/2011 2 weeks ($10 k) Built beam pipe and flanges (Kevin?)
4/18/2011 2 weeks ($10k) Chad builds and installs stands
1/11? 2 weeks ($10k) IAC engineers install beam line with magnets
2/11? Hunt Runs experiment
3/11? Sadiq emittance measurements
3/11? Sadiq and Khalid disassembles beam line for alignment
3/30/11 Order Gate Valve (4 week lead time)
4/4/11 Complete Beam Line CAD drawing (J. Ellis)
7/2011 3 days ($1k) Removed and reinstall Gun for alignment (Chad)
8/2011 Zero degree beam line aligned (Khalid, Sadiq)
1/25/2012 Target Motor from Empire Magnetics
1/25/2012 1 week ($5k) Target Chamber design (IAC engineer)
1/25/2012 Target Tungsten disks
2009-2012 $30 k 3 weeks of beam time

IAC investment: $66k

Indirects from DOE :

IAC personnel salary paid : $80k

Although not requested, magnet power supplies and a LabView control interface were installed by Chad. We were planning on using the old blue power supplies from the airport.

Positrons#HRRL_beam_Line_installation