Line 13: | Line 13: | ||
|7/2011 || 3 days ($1k) || Removed and reinstall Gun for alignment (Chad) | |7/2011 || 3 days ($1k) || Removed and reinstall Gun for alignment (Chad) | ||
|- | |- | ||
− | |8/2011 || Zero degree beam line aligned (Khalid, Sadiq) | + | |8/2011 || || Zero degree beam line aligned (Khalid, Sadiq) |
|- | |- | ||
− | |1/25/2012 || Target Motor from Empire Magnetics | + | |1/25/2012 || || Target Motor from Empire Magnetics |
|- | |- | ||
− | |1/25/2012 || Target Chamber | + | |1/25/2012 ||1 week ($5k) || Target Chamber design (IAC engineer) |
|- | |- | ||
− | |1/25/2012 || Target Tungsten disks | + | |1/25/2012 || || Target Tungsten disks |
|} | |} | ||
− | IAC investment: $ | + | IAC investment: $26k |
Indirects from DOE : | Indirects from DOE : | ||
+ | |||
+ | |||
+ | Although not requested, magnet power supplies and a LabView control interface were installed by Chad. | ||
[[Positrons#HRRL_beam_Line_installation]] | [[Positrons#HRRL_beam_Line_installation]] |
Revision as of 02:59, 17 October 2011
Completion Date | IAC | Task |
3/30/11 | Order Gate Valve (4 week lead time) | |
4/4/11 | Complete Beam Line CAD drawing (J. Ellis) | |
4/11/2011 | 2 weeks ($10 k) | Built beam pipe and flanges (Kevin?) |
4/18/2011 | 2 weeks ($10k) | Chad builds 4 stands |
7/2011 | 3 days ($1k) | Removed and reinstall Gun for alignment (Chad) |
8/2011 | Zero degree beam line aligned (Khalid, Sadiq) | |
1/25/2012 | Target Motor from Empire Magnetics | |
1/25/2012 | 1 week ($5k) | Target Chamber design (IAC engineer) |
1/25/2012 | Target Tungsten disks |
IAC investment: $26k
Indirects from DOE :
Although not requested, magnet power supplies and a LabView control interface were installed by Chad.