Difference between revisions of "HRRLPos Timeline Summary"
Jump to navigation
Jump to search
m (Protected "HRRLPos Timeline Summary" ([edit=autoconfirmed] (indefinite) [move=autoconfirmed] (indefinite) [read=autoconfirmed] (indefinite))) |
|
(No difference)
|
Revision as of 02:54, 17 October 2011
Completion Date | Task |
3/30/11 | Order Gate Valve (4 week lead time) |
4/4/11 | Complete Beam Line CAD drawing (J. Ellis) |
4/11/2011 | Built beam pipe and flanges (Kevin?) |
4/18/2011 | Chad builds 4 stands |
7/2011 | Removed Gun for alignment (Chad) |
8/2011 | Zero degree beam line aligned (Khalid, Sadiq) |
1/25/2012 | Target Motor from Empire Magnetics |
1/25/2012 | Target Chamber |
1/25/2012 | Target Tungsten disks |