| Line 5: | Line 5: | ||
| |3/30/11	||  Order Gate Valve (4 week lead time) | |3/30/11	||  Order Gate Valve (4 week lead time) | ||
| |- | |- | ||
| − | |4/4/11	        ||  Complete Beam Line CAD drawing | + | |4/4/11	        ||  Complete Beam Line CAD drawing (J. Ellis) | 
| |- | |- | ||
| |4/11/2011	|| Built beam pipe and flanges (Kevin?) | |4/11/2011	|| Built beam pipe and flanges (Kevin?) | ||
Revision as of 02:54, 17 October 2011
| Completion Date | Task | 
| 3/30/11 | Order Gate Valve (4 week lead time) | 
| 4/4/11 | Complete Beam Line CAD drawing (J. Ellis) | 
| 4/11/2011 | Built beam pipe and flanges (Kevin?) | 
| 4/18/2011 | Chad builds 4 stands | 
| 7/2011 | Removed Gun for alignment (Chad) | 
| 8/2011 | Zero degree beam line aligned (Khalid, Sadiq) | 
| 1/25/2012 | Target Motor from Empire Magnetics | 
| 1/25/2012 | Target Chamber | 
| 1/25/2012 | Target Tungsten disks |