| Completion Date | Task | 
| 3/30/11 | Order Gate Valve (4 week lead time) | 
| 4/4/11 | Complete Beam Line CAD drawing | 
| 4/11/2011 | Built beam pipe and flanges (Kevin?) | 
| 4/18/2011 | Chad builds X stands | 
| 7/2011 | Removed Gun for alignment (Chad) | 
| 8/2011 | Zero degree beam line aligned (Khalid, Sadiq) | 
| 1/25/2012 | Target Motor from Empire Magnetics | 
| 1/25/2012 | Target Chamber | 
| 1/25/2012 | Target Tungsten disks |