Timeline
 
Timeline
Line 5: Line 4:
 
7/30/08: Tony report's at Qweak collaboration meeting that GEM detector construction complete BUT the Charge collector Vendor has delayed delivery.
 
7/30/08: Tony report's at Qweak collaboration meeting that GEM detector construction complete BUT the Charge collector Vendor has delayed delivery.
 
8/30/08: Latech and W&M components to the Collaborative MRI grant expire, Virginia Tech receives an extension
 
8/30/08: Latech and W&M components to the Collaborative MRI grant expire, Virginia Tech receives an extension
 +
10/22/08: Charge collector arrives at ISU
 
10/23/08: Kathleen sends e-mail to Tony asking for requisition because MRI has expired and the GEM detector needs to be billed to the grant.
 
10/23/08: Kathleen sends e-mail to Tony asking for requisition because MRI has expired and the GEM detector needs to be billed to the grant.
10/30/08: Kathleen sends e-mail requesting that the chamber be sent so a property tag can be placed on it
+
10/30/08: Kathleen sends e-mail requesting that the chambers be sent so a property tag can be placed on it
 +
11/6/08 : after several exchanges a final invoice version (#5?)  is sent to LaTech
 +
11/19/08: Tony reports construction complete at Qweak collaboration meeting
 
11/24/08: 2 Qweak GEM detectors arrive at LaTex according to FedEx tracking.
 
11/24/08: 2 Qweak GEM detectors arrive at LaTex according to FedEx tracking.
 +
 +
 +
1/19/08: Klaus tells Greg smith that the last R1 milestone is delayed from March, 09 until Oct. 09.

Revision as of 17:58, 24 January 2009

Timeline

7/30/08: Tony report's at Qweak collaboration meeting that GEM detector construction complete BUT the Charge collector Vendor has delayed delivery. 8/30/08: Latech and W&M components to the Collaborative MRI grant expire, Virginia Tech receives an extension 10/22/08: Charge collector arrives at ISU 10/23/08: Kathleen sends e-mail to Tony asking for requisition because MRI has expired and the GEM detector needs to be billed to the grant. 10/30/08: Kathleen sends e-mail requesting that the chambers be sent so a property tag can be placed on it 11/6/08 : after several exchanges a final invoice version (#5?) is sent to LaTech 11/19/08: Tony reports construction complete at Qweak collaboration meeting 11/24/08: 2 Qweak GEM detectors arrive at LaTex according to FedEx tracking.


1/19/08: Klaus tells Greg smith that the last R1 milestone is delayed from March, 09 until Oct. 09.