Line 1: | Line 1: | ||
− | |||
Timeline | Timeline | ||
Line 5: | Line 4: | ||
7/30/08: Tony report's at Qweak collaboration meeting that GEM detector construction complete BUT the Charge collector Vendor has delayed delivery. | 7/30/08: Tony report's at Qweak collaboration meeting that GEM detector construction complete BUT the Charge collector Vendor has delayed delivery. | ||
8/30/08: Latech and W&M components to the Collaborative MRI grant expire, Virginia Tech receives an extension | 8/30/08: Latech and W&M components to the Collaborative MRI grant expire, Virginia Tech receives an extension | ||
+ | 10/22/08: Charge collector arrives at ISU | ||
10/23/08: Kathleen sends e-mail to Tony asking for requisition because MRI has expired and the GEM detector needs to be billed to the grant. | 10/23/08: Kathleen sends e-mail to Tony asking for requisition because MRI has expired and the GEM detector needs to be billed to the grant. | ||
− | 10/30/08: Kathleen sends e-mail requesting that the | + | 10/30/08: Kathleen sends e-mail requesting that the chambers be sent so a property tag can be placed on it |
+ | 11/6/08 : after several exchanges a final invoice version (#5?) is sent to LaTech | ||
+ | 11/19/08: Tony reports construction complete at Qweak collaboration meeting | ||
11/24/08: 2 Qweak GEM detectors arrive at LaTex according to FedEx tracking. | 11/24/08: 2 Qweak GEM detectors arrive at LaTex according to FedEx tracking. | ||
+ | |||
+ | |||
+ | 1/19/08: Klaus tells Greg smith that the last R1 milestone is delayed from March, 09 until Oct. 09. |
Revision as of 17:58, 24 January 2009
Timeline
7/30/08: Tony report's at Qweak collaboration meeting that GEM detector construction complete BUT the Charge collector Vendor has delayed delivery. 8/30/08: Latech and W&M components to the Collaborative MRI grant expire, Virginia Tech receives an extension 10/22/08: Charge collector arrives at ISU 10/23/08: Kathleen sends e-mail to Tony asking for requisition because MRI has expired and the GEM detector needs to be billed to the grant. 10/30/08: Kathleen sends e-mail requesting that the chambers be sent so a property tag can be placed on it 11/6/08 : after several exchanges a final invoice version (#5?) is sent to LaTech 11/19/08: Tony reports construction complete at Qweak collaboration meeting 11/24/08: 2 Qweak GEM detectors arrive at LaTex according to FedEx tracking.
1/19/08: Klaus tells Greg smith that the last R1 milestone is delayed from March, 09 until Oct. 09.