Difference between revisions of "Qweak R1 Proj Management"
Line 27: | Line 27: | ||
Date Milestone | Date Milestone | ||
Expected Delay Completed | Expected Delay Completed | ||
− | + | 7/08 Complete construction of GEM chamber | |
− | + | 8/08 Complete Installation of Front End Readout electronics | |
− | 1/ | + | 12/08 Complete Rotator control system |
− | + | 1/09 DAQ Back End Readout electronics completed | |
− | 3/ | + | 4/09 Final tests on Qweak Region 1 tracking system |
+ | 5/09 Deliver tracking system to JLAB | ||
+ | 3/10 Install tracking system in Hall C at JLAB | ||
[http://www.iac.isu.edu/mediawiki/index.php/Qweak Go Back] | [http://www.iac.isu.edu/mediawiki/index.php/Qweak Go Back] |
Revision as of 15:44, 29 July 2008
Project Leaders
Detector and Front End Electronics
The leader of this project reports on the R1 detector itself as well as the front end readout electronics.
Back End Electronics and Rotator
Th leader of this project will report on the back end readout electronics and the detector rotating system.
Man Power
JLAB tests Summer-09
The hope is to test the R1 detector during the Summer of 2009 at JLAB with a setup identical to what will be used in the Hall. This means having the all cables in place (with the proper lengths) to test timing. We need CODA setup with a VME crate that has a V1495 in it for readout. We need the scintillator for triggering. Paul King won't be available until after Mid June.
Commissioning shifts Summer-2010
These shifts wil take place during the Qweak comissioning phase (5/10). We will need someone who knows how to work with the VFAT board and the V1495. Specifically programming the parameters in both for timing , ie latency registers in the VFAT and the V1495. The procedure for this should be developed during the above tests at JLAB.
Tracking shifts
During the running of Qweak we probably don't want to be there for 6 months. We will need to write a document so a shift worker or tracking expert can do tracking measurement.
Timeline
Date Milestone Description
Date Milestone
Expected Delay Completed
7/08 Complete construction of GEM chamber
8/08 Complete Installation of Front End Readout electronics
12/08 Complete Rotator control system
1/09 DAQ Back End Readout electronics completed
4/09 Final tests on Qweak Region 1 tracking system
5/09 Deliver tracking system to JLAB
3/10 Install tracking system in Hall C at JLAB