Difference between revisions of "IAC 2-29-08"
(→B) |
(→B) |
||
Line 87: | Line 87: | ||
|441|| 0.0625" (-9.375k) from feedthrough , Sense wire at 1450 Volts, Gun voltage at 1.76 | |441|| 0.0625" (-9.375k) from feedthrough , Sense wire at 1450 Volts, Gun voltage at 1.76 | ||
|- | |- | ||
− | | | + | |442|| -5" (+240.625k) from feedthrough , Sense wire at 1450 Volts, Gun voltage at 1.76, try to get electrons missing chamber |
+ | |- | ||
+ | |443|| -3" (+140.625k) from feedthrough , Sense wire at 1450 Volts, Gun voltage at 1.76 | ||
|- | |- | ||
|} | |} |
Revision as of 17:49, 29 February 2008
Leap Day run
DC setup
This time the Sense wire HV is set to 1500 to start
90/10 ArCo2
HV settings | ||
Wire | Volts | current ( | A)
Sense | 1500 | |
Field | -750 | |
Guard | 750 |
DC preamp at 5.6 Volts
Beam Line Configuration
A 1/4 inch diameter collimater is placed in the experimental cell just after a Helium bag inserted in the wall. A 2 cm thick scintillator is place over the beam downstream side of the collimator aligned using a laser. A 1 kG magnet placed after the drift chambers deflects charged particles onto a large scintillator paddle. A coincidence is required between the two scintillators.
Increased beam energy from 10 MeV to 12 MeV due to expected energy loss in front scintillator.
Runs
A
Decided to increase beam current until up to 10% of events in front scintilaltor pass through magnet after drift chamber and hit back scintillator. Ran in OR mode so a software coincidence can be formed based on measurement in ADC15 (ADC14 in C convention).
Run # | Description |
431 | 0" from feedthrough , Sense wire at 1450 Volts, Gun voltage at 1.76 |
432 | 0" from feedthrough , Sense wire at 1500 Volts, Metalica (ADC6; C-convention) sees overflows and looks hot on scope compared to Plastika (ADC8: in ntuples),Gun voltage at 1.76 |
433 | -1" from feedthrough (beam should miss chamber), Sense wire at 1500 Volts, I see peds in Plastika but not metalica (Metalica is beam upstream of Plastika), The overflows are due to DC voltage/Gain being too high ,Gun voltage at 1.76 |
434 | 1" from feedthrough , Sense wire at 1500 Volts, Gun voltage at 1.76 |
435 | 2" from feedthrough , Sense wire at 1500 Volts, Gun voltage at 1.76 |
B
Change voltage on DC to values used on last day of January run 90/10 ArCo2
Drift Chamber HV
HV settings | ||
Cable # | Volts | Current (ma) |
Sense | 1456 | |
Field | 729 | |
Guard | 731 |
Run # | Description |
436 | 2" (-100k) from feedthrough , Sense wire at 1450 Volts, Gun voltage at 1.76, Less overflows in Metalica ADC |
437 | 4" (-200k) from feedthrough , Sense wire at 1450 Volts, Gun voltage at 1.76 |
438 | 1" (-50k) from feedthrough , Sense wire at 1450 Volts, Gun voltage at 1.76, visually inspected position and confirmed it was 1" from feedthrough |
439 | 0.5" (-25k) from feedthrough , Sense wire at 1450 Volts, Gun voltage at 1.76 |
440 | 0.25" (-12.5k) from feedthrough , Sense wire at 1450 Volts, Gun voltage at 1.76 |
441 | 0.0625" (-9.375k) from feedthrough , Sense wire at 1450 Volts, Gun voltage at 1.76 |
442 | -5" (+240.625k) from feedthrough , Sense wire at 1450 Volts, Gun voltage at 1.76, try to get electrons missing chamber |
443 | -3" (+140.625k) from feedthrough , Sense wire at 1450 Volts, Gun voltage at 1.76 |