Day 1.  December 3, 2007.
 
Day 1.  December 3, 2007.
  
Ira
+
 
 +
  Translator table setup
 +
 
 +
  Glass Slides at 10 cm, 30 cm, and 50 cm. 
 +
 
 +
  Beam spot size mapping in x and y with the Faraday Cup (FC) for z = 30cm from Window.  We will move the table in or out depending on whether the beam spot size is greater or smaller than 2.0 cm
 +
 
 +
  Linearity tests of the pickup coil and FC.
 +
 
 +
o Day 1: 5 hours of beamtime
 +
 
 +
1a) a first irradiation(blocks 1~4) ~5 hours Day 1
 +
2a) do a transparency measurement (blocks 1~4) ~3 hours Day 1
 +
3a) do a block (blocks 1~4) curing exposure to a blue light 24 hours day
 +
1 day
 +
o Day 2: 5 hours of beamtime

Revision as of 19:01, 20 November 2007

Day 1. December 3, 2007.


 Translator table setup 
 Glass Slides at 10 cm, 30 cm, and 50 cm.  
 Beam spot size mapping in x and y with the Faraday Cup (FC) for z = 30cm from Window.  We will move the table in or out depending on whether the beam spot size is greater or smaller than 2.0 cm
 Linearity tests of the pickup coil and FC.

o Day 1: 5 hours of beamtime

1a) a first irradiation(blocks 1~4) ~5 hours Day 1
2a) do a transparency measurement (blocks 1~4) ~3 hours Day 1
3a) do a block (blocks 1~4) curing exposure to a blue light 24 hours day

1 day o Day 2: 5 hours of beamtime