===To do list===
 
===To do list===
  
- Add dual timer configuration to plateau page (X)
+
* Add dual timer configuration to plateau page (X)
  
- Continue to fine tune operating point of NaI detector
+
* Continue to fine tune operating point of NaI detector and upload plateaus/signal:noise plots
  
- NaI attenuation measurements (with BorAl and try different types of poly (unborated, lavender, green))
+
* NaI attenuation measurements (with BorAl and try different types of poly (unborated, lavender, green))
  
- Begin experimental setup in clean room  
+
* Begin experimental setup in clean room  
  
- Find signal to noise ratio
+
* Find signal to noise ratio
  
- Test HPGe detector
+
* Test HPGe detector
  
- Complete latest assigned training module (X)
+
* Complete latest assigned training module (X)
  
- Speak to Roy Dunker who has agreed to let us use a second HPGe detector for back-to-back measurements in later phase of feasibility studies at ISU (X)
+
* Speak to Roy Dunker who has agreed to let us use a second HPGe detector for back-to-back measurements in later phase of feasibility studies at ISU (X)
 
 
- How much lead to shield 200KeV gamma? How much poly to thermalize 2MeV neutrons? (DD generator shielding)
 
  
 +
* How much lead to shield 200KeV gamma? How much poly to thermalize 2MeV neutrons? (DD generator shielding)
  
 +
* Move painted lead bricks to clean room (X)
  
  
 
----
 
----
 
[[PAS_Experiment]]
 
[[PAS_Experiment]]

Revision as of 23:51, 1 June 2021

Notes from biweekly meetings

5/27/21

To do list

  • Add dual timer configuration to plateau page (X)
  • Continue to fine tune operating point of NaI detector and upload plateaus/signal:noise plots
  • NaI attenuation measurements (with BorAl and try different types of poly (unborated, lavender, green))
  • Begin experimental setup in clean room
  • Find signal to noise ratio
  • Test HPGe detector
  • Complete latest assigned training module (X)
  • Speak to Roy Dunker who has agreed to let us use a second HPGe detector for back-to-back measurements in later phase of feasibility studies at ISU (X)
  • How much lead to shield 200KeV gamma? How much poly to thermalize 2MeV neutrons? (DD generator shielding)
  • Move painted lead bricks to clean room (X)