Difference between revisions of "201112 R1ProgressRep"

From New IAC Wiki
Jump to navigation Jump to search
 
(8 intermediate revisions by the same user not shown)
Line 45: Line 45:
 
42 sense wires were strung today.
 
42 sense wires were strung today.
  
[[file:20111209_Temp1.png | 400 px]]
+
=12/12/11=
 +
 
 +
48 sense wires were strung today.
 +
 
 +
[[file:20111212_Temp1.png | 400 px]]
 +
 
 +
=12/13/11=
 +
 
 +
84 sense wires were strung today.
 +
 
 +
[[file:20111213_Temp1.png | 400 px]]
 +
 
 +
=12/14/11=
 +
 
 +
84 sense wires were strung today.
 +
 
 +
=12/15/11=
 +
 
 +
The installation of the large roll up doors began today instead of Friday.  The scheduled completion of the doors is on Tuesday, December 20th.  Stringing has been suspended until the doors have been installed.
 +
 
 +
=12/19/11=
 +
 
 +
The door installation was completed early.
 +
 
 +
I spent some time in the morning cleaning up.  The pre-filter for the changing room appears to be very dirty.  I will plan on replacing these filters again once we return from the holiday break.
 +
 
 +
27 sense wires were strung today.
 +
 
 +
=12/20/11=
 +
 
 +
42 sense wires were strung today.
 +
 
 +
=12/21/11=
 +
 
 +
36 sense wires were strung today.
 +
 
 +
=12/22/11=
 +
 
 +
27 sense wires were strung today.

Latest revision as of 22:50, 22 December 2011

12/1/11

91 wires were strung today.

20111201 Temp1.png

12/2/11

97 wires were strung today. All field wires are strung and the final tensioner has been removed.

20111202 Temp1.png

12/3/11

Weekly trend measurement was done today.

12/5/11

Prior to rotating the chamber, I decided to do a thorough visual inspection to ensure no crossed wires. During this inspection, several wires were found that had kinks in them. These wires were replaced. Tensions were measured also.

Chamber has been rotated. Sense wire stringing has begun.

22 sense wires were strung today.

20111205 Temp1.png

12/6/11

84 sense wires were strung today.

12/7/11

45 sense wires were strung today.

20111207 Temp1.png

12/8/11

72 sense wires were strung today.

20111208 Temp1.png

12/9/11

42 sense wires were strung today.

12/12/11

48 sense wires were strung today.

20111212 Temp1.png

12/13/11

84 sense wires were strung today.

20111213 Temp1.png

12/14/11

84 sense wires were strung today.

12/15/11

The installation of the large roll up doors began today instead of Friday. The scheduled completion of the doors is on Tuesday, December 20th. Stringing has been suspended until the doors have been installed.

12/19/11

The door installation was completed early.

I spent some time in the morning cleaning up. The pre-filter for the changing room appears to be very dirty. I will plan on replacing these filters again once we return from the holiday break.

27 sense wires were strung today.

12/20/11

42 sense wires were strung today.

12/21/11

36 sense wires were strung today.

12/22/11

27 sense wires were strung today.