| − | |  | + | |9/10	||  2 weeks ($10k) ||Chad builds and installs  stands  | 
|-  | |-  | ||
| − | |  | + | |10/10	|| 2 days ($1k) ||IAC engineers move HRRL to new location  | 
|-  | |-  | ||
| − | |  | + | |10/10	|| 2 weeks ($10 k) ||Built beam pipe and flanges (Kevin?)  | 
|-  | |-  | ||
| − | |  | + | |10/10	|| 2 weeks ($10k) ||IAC engineers install beam line with magnets  | 
|-  | |-  | ||
| − | |  | + | |11/9/10	|| || RF conditioning  | 
|-  | |-  | ||
| − | |3/11  | + | |11/2910-12/15/10	||  ||NRF experiment with moved HRRL  | 
| + | |-  | ||
| + | |2/16/11||  ||OTR test with beam  | ||
| + | |-  | ||
| + | |3/3/11||  ||OTR test with beam  | ||
| + | |-  | ||
| + | |3/14/11-3/18/11	||  ||Sadiq emittance measurements.  Beam  misalignment was discovered.  It was discovered later during the 8/11 alignment that the beam line center was 1.5 cm below the center of the experimental cell port (hole through the wall).  | ||
|-  | |-  | ||
|7/2011	        || 3 days ($1k) || Removed and reinstall Gun for alignment (Chad)  | |7/2011	        || 3 days ($1k) || Removed and reinstall Gun for alignment (Chad)  | ||
| Line 26: | Line 32: | ||
|-  | |-  | ||
|8/2011	        || ||  3 weeks Zero degree beam line aligned (Khalid, Sadiq)  | |8/2011	        || ||  3 weeks Zero degree beam line aligned (Khalid, Sadiq)  | ||
| + | |-  | ||
| + | |8/2011	        || $500 || 1 day IAC engineers assemble pump down zero degree beam line. Gate valve and OTR Flag  installed  | ||
|-  | |-  | ||
|10/2011	        || ||  1 week Map 2nd Dipole  (Khalid, Sadiq)  | |10/2011	        || ||  1 week Map 2nd Dipole  (Khalid, Sadiq)  | ||
| + | |-  | ||
| + | |10/2011	        || ||  $1500 Order 2nd Ion Pump for HRRL [[File:HRRLIONPumpQUote102011.pdf]]  | ||
| + | |-  | ||
| + | |10/2011	        || ||  Order Ion Pump Power supply and connectors  | ||
| + | |-  | ||
| + | |19/10/2011	|| ||  [[https://wiki.iac.isu.edu/index.php/Instruments_and_Equipments# Beam_Pipe_for_Quad7 Order 2 Flanges for quad7 beampipe from Duniway]]  | ||
| + | |-  | ||
| + | |20/10/2011	|| || Order beampipe for quad7 and beampipe for 90 degree extension  | ||
| + | |-  | ||
| + | |21/10/2011	|| || Beam pipe for quad7, ion pump, and 90 degree extension brought back to beamlab (Sadiq)  | ||
| + | |-  | ||
| + | |21/10/2011	|| || [[https://wiki.iac.isu.edu/index.php/90_degree_beamline_extension Beam line design for 90 extension was done. Purchase list created. Asked Kevin for double check.  (Sadiq) ]]  | ||
| + | |-  | ||
| + | |21/10/2011	|| || [[https://wiki.iac.isu.edu/index.php/Instruments_and_Equipments#3rd_JLab_Flag  3rd Jlab flag tested. No, electronic switch. It works. Need to buy a 10-hole-flange. (Sadiq)]]  | ||
| + | |-  | ||
| + | |24/10/2011	|| || HRRL experimental and accelerator areas were cleaned.  (Sadiq and Sam) ]]  | ||
| + | |-  | ||
| + | |24/10/2011	|| || [[https://wiki.iac.isu.edu/index.php/90_degree_beamline_extension Kevin verified 90 degree extension beamline design. Flange for Jlab flag quoted. Now all 90 degree extension beamline parts ready to be ordered. (Sadiq) ]]  | ||
| + | |-  | ||
| + | |25/10/2011	|| || [[https://wiki.iac.isu.edu/index.php/Instruments_and_Equipments#Parts_to_build_control_circuit Received Energy Slit control circuit parts from Digikey]]  | ||
| + | |-  | ||
| + | |11/01/2011	|| || 2 Flanges for quad 7 received (Dumiway). Ion pump Received (Duniway).  | ||
| + | |-  | ||
| + | |11/03/2011	|| || 2 Flanges and 2.5" pipe for quad 7 were given to engineer (Myles Whiting) in Engineering department to make beam pipe.   | ||
|-  | |-  | ||
|1/25/2012	|| || Target Motor  from Empire Magnetics  | |1/25/2012	|| || Target Motor  from Empire Magnetics  | ||
| Line 38: | Line 70: | ||
|}  | |}  | ||
| − | IAC investment: $  | + | IAC investment: $67.5k  | 
| − | Indirects from DOE :  | + | Indirects from DOE : $90k  | 
IAC personnel salary paid : $80k  | IAC personnel salary paid : $80k  | ||
Latest revision as of 20:45, 3 November 2011
| Completion Date | IAC | Task | 
| 9/10 | 2 weeks ($10k) | Chad builds and installs stands | 
| 10/10 | 2 days ($1k) | IAC engineers move HRRL to new location | 
| 10/10 | 2 weeks ($10 k) | Built beam pipe and flanges (Kevin?) | 
| 10/10 | 2 weeks ($10k) | IAC engineers install beam line with magnets | 
| 11/9/10 | RF conditioning | |
| 11/2910-12/15/10 | NRF experiment with moved HRRL | |
| 2/16/11 | OTR test with beam | |
| 3/3/11 | OTR test with beam | |
| 3/14/11-3/18/11 | Sadiq emittance measurements. Beam misalignment was discovered. It was discovered later during the 8/11 alignment that the beam line center was 1.5 cm below the center of the experimental cell port (hole through the wall). | |
| 7/2011 | 3 days ($1k) | Removed and reinstall Gun for alignment (Chad) | 
| 3/11? | Sadiq and Khalid disassembles beam line for alignment | |
| 3/30/11 | Order Gate Valve (4 week lead time) | |
| 4/4/11 | Complete Beam Line CAD drawing (J. Ellis) | |
| 8/2011 | 1 week Mapped one Quad (Khalid, Sadiq) | |
| 8/2011 | 3 weeks Zero degree beam line aligned (Khalid, Sadiq) | |
| 8/2011 | $500 | 1 day IAC engineers assemble pump down zero degree beam line. Gate valve and OTR Flag installed | 
| 10/2011 | 1 week Map 2nd Dipole (Khalid, Sadiq) | |
| 10/2011 | $1500 Order 2nd Ion Pump for HRRL File:HRRLIONPumpQUote102011.pdf | |
| 10/2011 | Order Ion Pump Power supply and connectors | |
| 19/10/2011 | [Beam_Pipe_for_Quad7 Order 2 Flanges for quad7 beampipe from Duniway] | |
| 20/10/2011 | Order beampipe for quad7 and beampipe for 90 degree extension | |
| 21/10/2011 | Beam pipe for quad7, ion pump, and 90 degree extension brought back to beamlab (Sadiq) | |
| 21/10/2011 | [Beam line design for 90 extension was done. Purchase list created. Asked Kevin for double check. (Sadiq) ] | |
| 21/10/2011 | [3rd Jlab flag tested. No, electronic switch. It works. Need to buy a 10-hole-flange. (Sadiq)] | |
| 24/10/2011 | HRRL experimental and accelerator areas were cleaned. (Sadiq and Sam) ]] | |
| 24/10/2011 | [Kevin verified 90 degree extension beamline design. Flange for Jlab flag quoted. Now all 90 degree extension beamline parts ready to be ordered. (Sadiq) ] | |
| 25/10/2011 | [Received Energy Slit control circuit parts from Digikey] | |
| 11/01/2011 | 2 Flanges for quad 7 received (Dumiway). Ion pump Received (Duniway). | |
| 11/03/2011 | 2 Flanges and 2.5" pipe for quad 7 were given to engineer (Myles Whiting) in Engineering department to make beam pipe. | |
| 1/25/2012 | Target Motor from Empire Magnetics | |
| 1/25/2012 | 1 week ($5k) | Target Chamber design (IAC engineer) | 
| 1/25/2012 | Target Tungsten disks | |
| 2009-2012 | $30 k | 3 weeks of beam time | 
IAC investment: $67.5k
Indirects from DOE : $90k
IAC personnel salary paid : $80k