| Line 1: | Line 1: | ||
{| border="1" |cellpadding="20" cellspacing="0 | {| border="1" |cellpadding="20" cellspacing="0 | ||
|- | |- | ||
| − | | Completion Date || Task | + | | Completion Date || IAC ||Task |
|- | |- | ||
| − | | | + | |9/10 || 2 weeks ($10k) ||Chad builds and installs stands |
|- | |- | ||
| − | | | + | |10/10 || 2 days ($1k) ||IAC engineers move HRRL to new location |
|- | |- | ||
| − | | | + | |10/10 || 2 weeks ($10 k) ||Built beam pipe and flanges (Kevin?) |
|- | |- | ||
| − | | | + | |10/10 || 2 weeks ($10k) ||IAC engineers install beam line with magnets |
|- | |- | ||
| − | | | + | |11/9/10 || || RF conditioning |
|- | |- | ||
| − | | | + | |11/2910-12/15/10 || ||NRF experiment with moved HRRL |
|- | |- | ||
| − | | | + | |2/16/11|| ||OTR test with beam |
|- | |- | ||
| − | | | + | |3/3/11|| ||OTR test with beam |
|- | |- | ||
| − | |1/25/2012 || Target Tungsten disks | + | |3/14/11-3/18/11 || ||Sadiq emittance measurements. Beam misalignment was discovered. It was discovered later during the 8/11 alignment that the beam line center was 1.5 cm below the center of the experimental cell port (hole through the wall). |
| + | |- | ||
| + | |7/2011 || 3 days ($1k) || Removed and reinstall Gun for alignment (Chad) | ||
| + | |- | ||
| + | |3/11? || ||Sadiq and Khalid disassembles beam line for alignment | ||
| + | |- | ||
| + | |3/30/11 || ||Order Gate Valve (4 week lead time) | ||
| + | |- | ||
| + | |4/4/11 || ||Complete Beam Line CAD drawing (J. Ellis) | ||
| + | |- | ||
| + | |8/2011 || || 1 week Mapped one Quad (Khalid, Sadiq) | ||
| + | |- | ||
| + | |8/2011 || || 3 weeks Zero degree beam line aligned (Khalid, Sadiq) | ||
| + | |- | ||
| + | |8/2011 || $500 || 1 day IAC engineers assemble pump down zero degree beam line. Gate valve and OTR Flag installed | ||
| + | |- | ||
| + | |10/2011 || || 1 week Map 2nd Dipole (Khalid, Sadiq) | ||
| + | |- | ||
| + | |10/2011 || || $1500 Order 2nd Ion Pump for HRRL [[File:HRRLIONPumpQUote102011.pdf]] | ||
| + | |- | ||
| + | |10/2011 || || Order Ion Pump Power supply and connectors | ||
| + | |- | ||
| + | |19/10/2011 || || [[https://wiki.iac.isu.edu/index.php/Instruments_and_Equipments# Beam_Pipe_for_Quad7 Order 2 Flanges for quad7 beampipe from Duniway]] | ||
| + | |- | ||
| + | |20/10/2011 || || Order beampipe for quad7 and beampipe for 90 degree extension | ||
| + | |- | ||
| + | |21/10/2011 || || Beam pipe for quad7, ion pump, and 90 degree extension brought back to beamlab (Sadiq) | ||
| + | |- | ||
| + | |21/10/2011 || || [[https://wiki.iac.isu.edu/index.php/90_degree_beamline_extension Beam line design for 90 extension was done. Purchase list created. Asked Kevin for double check. (Sadiq) ]] | ||
| + | |- | ||
| + | |21/10/2011 || || [[https://wiki.iac.isu.edu/index.php/Instruments_and_Equipments#3rd_JLab_Flag 3rd Jlab flag tested. No, electronic switch. It works. Need to buy a 10-hole-flange. (Sadiq)]] | ||
| + | |- | ||
| + | |24/10/2011 || || HRRL experimental and accelerator areas were cleaned. (Sadiq and Sam) ]] | ||
| + | |- | ||
| + | |24/10/2011 || || [[https://wiki.iac.isu.edu/index.php/90_degree_beamline_extension Kevin verified 90 degree extension beamline design. Flange for Jlab flag quoted. Now all 90 degree extension beamline parts ready to be ordered. (Sadiq) ]] | ||
| + | |- | ||
| + | |25/10/2011 || || [[https://wiki.iac.isu.edu/index.php/Instruments_and_Equipments#Parts_to_build_control_circuit Received Energy Slit control circuit parts from Digikey]] | ||
| + | |- | ||
| + | |11/01/2011 || || 2 Flanges for quad 7 received (Dumiway). Ion pump Received (Duniway). | ||
| + | |- | ||
| + | |11/03/2011 || || 2 Flanges and 2.5" pipe for quad 7 were given to engineer (Myles Whiting) in Engineering department to make beam pipe. | ||
| + | |- | ||
| + | |1/25/2012 || || Target Motor from Empire Magnetics | ||
| + | |- | ||
| + | |1/25/2012 ||1 week ($5k) || Target Chamber design (IAC engineer) | ||
| + | |- | ||
| + | |1/25/2012 || || Target Tungsten disks | ||
| + | |- | ||
| + | |2009-2012 ||$30 k || 3 weeks of beam time | ||
|} | |} | ||
| + | IAC investment: $67.5k | ||
| + | |||
| + | Indirects from DOE : $90k | ||
| + | |||
| + | IAC personnel salary paid : $80k | ||
| + | Although not requested, magnet power supplies and a LabView control interface were installed by Chad. We were planning on using the old blue power supplies from the airport. | ||
[[Positrons#HRRL_beam_Line_installation]] | [[Positrons#HRRL_beam_Line_installation]] | ||
Latest revision as of 20:45, 3 November 2011
| Completion Date | IAC | Task |
| 9/10 | 2 weeks ($10k) | Chad builds and installs stands |
| 10/10 | 2 days ($1k) | IAC engineers move HRRL to new location |
| 10/10 | 2 weeks ($10 k) | Built beam pipe and flanges (Kevin?) |
| 10/10 | 2 weeks ($10k) | IAC engineers install beam line with magnets |
| 11/9/10 | RF conditioning | |
| 11/2910-12/15/10 | NRF experiment with moved HRRL | |
| 2/16/11 | OTR test with beam | |
| 3/3/11 | OTR test with beam | |
| 3/14/11-3/18/11 | Sadiq emittance measurements. Beam misalignment was discovered. It was discovered later during the 8/11 alignment that the beam line center was 1.5 cm below the center of the experimental cell port (hole through the wall). | |
| 7/2011 | 3 days ($1k) | Removed and reinstall Gun for alignment (Chad) |
| 3/11? | Sadiq and Khalid disassembles beam line for alignment | |
| 3/30/11 | Order Gate Valve (4 week lead time) | |
| 4/4/11 | Complete Beam Line CAD drawing (J. Ellis) | |
| 8/2011 | 1 week Mapped one Quad (Khalid, Sadiq) | |
| 8/2011 | 3 weeks Zero degree beam line aligned (Khalid, Sadiq) | |
| 8/2011 | $500 | 1 day IAC engineers assemble pump down zero degree beam line. Gate valve and OTR Flag installed |
| 10/2011 | 1 week Map 2nd Dipole (Khalid, Sadiq) | |
| 10/2011 | $1500 Order 2nd Ion Pump for HRRL File:HRRLIONPumpQUote102011.pdf | |
| 10/2011 | Order Ion Pump Power supply and connectors | |
| 19/10/2011 | [Beam_Pipe_for_Quad7 Order 2 Flanges for quad7 beampipe from Duniway] | |
| 20/10/2011 | Order beampipe for quad7 and beampipe for 90 degree extension | |
| 21/10/2011 | Beam pipe for quad7, ion pump, and 90 degree extension brought back to beamlab (Sadiq) | |
| 21/10/2011 | [Beam line design for 90 extension was done. Purchase list created. Asked Kevin for double check. (Sadiq) ] | |
| 21/10/2011 | [3rd Jlab flag tested. No, electronic switch. It works. Need to buy a 10-hole-flange. (Sadiq)] | |
| 24/10/2011 | HRRL experimental and accelerator areas were cleaned. (Sadiq and Sam) ]] | |
| 24/10/2011 | [Kevin verified 90 degree extension beamline design. Flange for Jlab flag quoted. Now all 90 degree extension beamline parts ready to be ordered. (Sadiq) ] | |
| 25/10/2011 | [Received Energy Slit control circuit parts from Digikey] | |
| 11/01/2011 | 2 Flanges for quad 7 received (Dumiway). Ion pump Received (Duniway). | |
| 11/03/2011 | 2 Flanges and 2.5" pipe for quad 7 were given to engineer (Myles Whiting) in Engineering department to make beam pipe. | |
| 1/25/2012 | Target Motor from Empire Magnetics | |
| 1/25/2012 | 1 week ($5k) | Target Chamber design (IAC engineer) |
| 1/25/2012 | Target Tungsten disks | |
| 2009-2012 | $30 k | 3 weeks of beam time |
IAC investment: $67.5k
Indirects from DOE : $90k
IAC personnel salary paid : $80k
Although not requested, magnet power supplies and a LabView control interface were installed by Chad. We were planning on using the old blue power supplies from the airport.