= Project Leaders=
 
= Project Leaders=
 
==Detector and Front End Electronics==
 
==Detector and Front End Electronics==
 +
 +
The leader of this project reports on the R1 detector itself as well as the front end readout electronics.
 +
 
==Back End Electronics and Rotator==
 
==Back End Electronics and Rotator==
 +
 +
Th leader of this project will report on the back end readout electronics and the detector rotating system.
  
 
=Man Power=
 
=Man Power=
== JLAB tests==
+
== JLAB tests Summer-09==
  
 
The hope is to test the R1 detector during the Summer of 2009 at JLAB with a setup identical to what will be used in the Hall.  This means having the all cables in place (with the proper lengths) to test timing.  We need CODA setup with a VME crate that has a V1495 in it for readout.  We need the scintillator for triggering.  Paul King won't be available until after Mid June.
 
The hope is to test the R1 detector during the Summer of 2009 at JLAB with a setup identical to what will be used in the Hall.  This means having the all cables in place (with the proper lengths) to test timing.  We need CODA setup with a VME crate that has a V1495 in it for readout.  We need the scintillator for triggering.  Paul King won't be available until after Mid June.
  
 +
==Commissioning shifts Summer-2010==
  
==Commissioning shifts==
+
These shifts wil take place during the Qweak comissioning phase (5/10).  We will need someone who knows how to work with the VFAT board and the V1495.  Specifically programming the parameters in both for timing , ie latency registers in the VFAT and the V1495.  The procedure for this should be developed during the above tests at JLAB.
  
These shifts wil take place during the Qweak comissioning phase
+
==Tracking shifts==
  
# Tracking shifts
+
During the running of Qweak we probably don't want to be there for 6 months.  We will need to write a document so a shift worker or tracking expert  can do tracking measurement.
#Writing the tracking document for shift takers.
 
  
 
=Timeline=
 
=Timeline=
Line 20: Line 25:
  
  
[http://www.iac.isu.edu/mediawiki/index.php/Qweak Go Back]
+
{| border="1"  |cellpadding="20" cellspacing="0
 +
|Date
 +
|colspan= "2" | Milestone
 +
|-
 +
| Expected||  Completed || Desc.
 +
|-
 +
|7/08 || 11/14/08 ||Complete Construction of the GEM chamber
 +
|-
 +
|8/08 || 3/09  || Observe GEM detector trigger signal using ionization source
 +
|-
 +
|8/08|| 5/18/09  ||Install Front End electronics
 +
|-
 +
|12/08||  || Complete Rotator control system
 +
|-
 +
|1/09 ||  || DAQ Back End readout electronics complete
 +
|-
 +
|4/09 ||  || Final tests on Qweak Region 1 tracking system
 +
|-
 +
|5/09||  || Deliver Tracking system to JLAB
 +
|-
 +
|3/10||  || Install Tracking System in Hall C
 +
|}
 +
 
 +
 
 +
 
 +
[http://wiki.iac.isu.edu/index.php/Qweak Go Back][[Qweak]]

Latest revision as of 13:56, 18 May 2009

Project Leaders

Detector and Front End Electronics

The leader of this project reports on the R1 detector itself as well as the front end readout electronics.

Back End Electronics and Rotator

Th leader of this project will report on the back end readout electronics and the detector rotating system.

Man Power

JLAB tests Summer-09

The hope is to test the R1 detector during the Summer of 2009 at JLAB with a setup identical to what will be used in the Hall. This means having the all cables in place (with the proper lengths) to test timing. We need CODA setup with a VME crate that has a V1495 in it for readout. We need the scintillator for triggering. Paul King won't be available until after Mid June.

Commissioning shifts Summer-2010

These shifts wil take place during the Qweak comissioning phase (5/10). We will need someone who knows how to work with the VFAT board and the V1495. Specifically programming the parameters in both for timing , ie latency registers in the VFAT and the V1495. The procedure for this should be developed during the above tests at JLAB.

Tracking shifts

During the running of Qweak we probably don't want to be there for 6 months. We will need to write a document so a shift worker or tracking expert can do tracking measurement.

Timeline

Date Milestone Description


Date Milestone
Expected Completed Desc.
7/08 11/14/08 Complete Construction of the GEM chamber
8/08 3/09 Observe GEM detector trigger signal using ionization source
8/08 5/18/09 Install Front End electronics
12/08 Complete Rotator control system
1/09 DAQ Back End readout electronics complete
4/09 Final tests on Qweak Region 1 tracking system
5/09 Deliver Tracking system to JLAB
3/10 Install Tracking System in Hall C