Difference between revisions of "HRRL Simulations"
(118 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
+ | [http://wiki.iac.isu.edu/index.php/HRRL Go Back] | ||
+ | |||
+ | |||
+ | Dose Goal: 25 mRem/year to public (after ceiling assuming occupied 1/16 of the time) and 2 mrem/hr. | ||
+ | |||
Mark Balzer: 282-5652 | Mark Balzer: 282-5652 | ||
Line 8: | Line 13: | ||
Low energy gamma cutoff = 60 keV | Low energy gamma cutoff = 60 keV | ||
+ | |||
+ | = HRRL Running Conditions= | ||
+ | |||
+ | ==8 mA == | ||
+ | A 2" x 4" x 8 " Al brick was used as a FC by placing it at the exit port of the HRRL after a 90 degree magnet bends electrons towards the HRRL experimental Cell. The output of a FC after the 90 degree bend at a beam energy of 3 MeV, I= 8 mA, pulse width = 25 ns, and rep rate of 60 Hz is shown in the scope picture below. | ||
+ | |||
+ | [[Image:HRRL_3MeV_FC_output_10_10_08.png|200px]] | ||
+ | |||
+ | An accelerator operator will be able to tune the beam at this setting. | ||
+ | |||
+ | =Copper Simulation= | ||
+ | |||
+ | A 10 m x 10m x 10m HURL experimental cells was simulated in which a 2 mm Copper target representing detectors was installed 1 m from the beam upstream wall and centered in the remaining dimensions of the room. The ceiling was set 3m above the copper target. | ||
+ | |||
+ | == 3 MeV == | ||
+ | |||
+ | A comparison between MCNP-X and GEANT4: Both simulations threw <math>10^6</math> electrons onto a 2 mm thick Copper target located in the HRRL experimental Cell. | ||
+ | |||
+ | {| border="1" |cellpadding="20" cellspacing="0 | ||
+ | |- | ||
+ | | Simulation || Gamma Energy deposited per <math>10^6</math> incident <math>e^-</math> | ||
+ | |- | ||
+ | | || Inside Cell || above 6" thick concrete Cell ceiling || Ion Chamber in HRRL Cell || Peak current limit at 25 ns and 1kHz | ||
+ | |- | ||
+ | |MCNPX || <math>2.53 \times 10^4</math> MeV (rad/C)|| <math>1.3 \times 10^3</math> MeV (rad/C) || <math>9.5 \times 10^{-18} rem/e</math> || <math>7.9</math> mA | ||
+ | |- | ||
+ | |GEANT4||<math>3.1 \times 10^4</math> MeV (rad/C)|| <math>5.6 \times 10^3</math> MeV (rad/C) | ||
+ | |} | ||
+ | |||
+ | Converting the energy from MeV to Joules | ||
+ | |||
+ | :<math>1 \times 10^4 MeV \times \frac{1.6 \times 10^{-19} J }{10^{-6} MeV} = 1.6 \times 10^{-9} J</math> | ||
+ | |||
+ | In terms of the energy per beam current charge we would have | ||
+ | |||
+ | :<math>\frac{ 1.6 \times 10^{-9} J}{10^6 e^-} \times \frac{1 e^-}{1.6 \times 10^{-19} C} = \frac { 10 krad}{C}</math> | ||
+ | |||
+ | (I assume a 100 kg person ( 1 rad = 1 J/100 kg) Units are not consistent. There is a mass unit missing in this conversion. Vakho) | ||
+ | |||
+ | Average Current for a 2mrad/hr dose limit | ||
+ | |||
+ | :<math>\frac{ 2 \times 10^{-3} rad}{3600 sec} \times \frac{1 C }{10^{4} rad} = 5.6 \times 10^{-11} Coul/sec = 56 pA = 0.05 nA</math> | ||
+ | |||
+ | How can you get 56 pA from the HRRL? | ||
+ | |||
+ | Currently you can see an 8 mA current on a FC with a 25 nSecond pulse width. | ||
+ | |||
+ | : <math>\Rightarrow 8 \times 10^{-3} Couls/sec \times 25 \times 10^{-9} seconds = 2 \times 10^{-10} Coul</math> | ||
+ | |||
+ | Therefore: Restricting to HRRL to 2 mA peak currents with 25 nSec pulse widths and 1 Hz should keep the dose beyond a 6" concrete ceiling below 2 mrad/hr. 2 mA peak HRRL currents have been [http://www.iac.isu.edu/mediawiki/index.php/5-19-08#FC_performance measured before] using a FC from JLab. | ||
+ | |||
+ | |||
+ | |||
+ | ; What running conditions will result in less than 25 mrad of dose for 2000 hours (1 year) of operation | ||
+ | :<math>\frac{ 25 \times 10^{-3} rad}{2000 hours} \times \frac{ 1 hr}{3600 sec} \frac{1 C }{10^{4} rad} = 3.47 \times 10^{-13} Coul/sec</math> | ||
+ | : <math>\Rightarrow I_{HRRL}^{peak} = 0.008</math> mA | ||
+ | |||
+ | [[Image:E_Gammas_3MeV_e-_Cu_MCNPX.jpg | 400 px]] | ||
+ | [[Image:E_Gammas_3MeV_e-_Cu_GEANT4.gif | 400 px]] | ||
+ | |||
+ | [[Image:E_Gammas_Above6incCeiling_3MeV_e-_Cu_MCNPX.jpg | 400 px]] | ||
+ | [[Image:E_Gammas_Above6incCeiling_3MeV_e-_Cu_GEANT4.gif | 400 px]] | ||
+ | |||
+ | |||
+ | The above predictions only considered gammas with energies above 100 keV. With the 100 keV cut removed I still see less than <math>10^4</math> MeV (6770 MeV) of deposited energy per <math> 10^6</math> incident 3 MeV electrons. | ||
+ | |||
+ | [[Image:E_Gammas_Above6incCeilingNoCut_3MeV_e-_Cu_GEANT4.gif | 400 px]] | ||
+ | |||
+ | == 7 MeV == | ||
+ | |||
+ | {| border="1" |cellpadding="20" cellspacing="0 | ||
+ | |- | ||
+ | |Simulation || Gamma Energy deposited per <math>10^6</math> incident <math>e^-</math> | ||
+ | |- | ||
+ | | || Inside Cell || above 6" thick concrete Cell ceiling || Ion Chamber in HRRL Cell || Peak current limit at 25 ns and 1 kHz | ||
+ | |- | ||
+ | |MCNPX || <math>1.41 \times 10^5</math> MeV (rad/C)|| <math>1.38 \times 10^4</math> MeV || <math>6.2 \times 10^{-17} rem/e</math> || <math>0.6</math> mA | ||
+ | |- | ||
+ | |GEANT4||<math> 1.01 \times 10^5</math> MeV (rad/C)|| | ||
+ | |} | ||
+ | |||
+ | [[Image:GammaProfile_10-14-08.gif | 200 px]] | ||
+ | |||
+ | The GEANT4 histograms below are from 100 k Events not 1 Million like Vakhos. | ||
+ | |||
+ | |||
+ | [[Image:Gammas_7MeV_e-_Cu_100kEvents_10-14-08.gif | 200 px]] | ||
+ | |||
+ | [[Image:Gammas_.g.t.100keV_7MeV_e-_Cu_100kEvents_10-14-08.gif | 200 px]] | ||
+ | |||
+ | [[Image:E_Gammas_7MeV_e-_Cu_MCNPX.jpg | 400 px | 200 px]] | ||
+ | |||
+ | [[Image:E_Gammas_Above_Concrete_7MeV_e-_Cu_MCNPX.jpg | 400 px | 200 px]] | ||
=Tungsten SImulation= | =Tungsten SImulation= | ||
Line 76: | Line 174: | ||
==Run 2: Ceiling Penetration== | ==Run 2: Ceiling Penetration== | ||
− | ===Setup== | + | ===Setup=== |
The picture below shows the simulation World volume. A red electron beam enters the HRRL experimental cell from the left side and hits a 2 mm thick Tungsten target shown as the white vertical line inside the white inner box. The yellow box is a detector tracking cell. The roof is shown as 2 horizontal lines near the top of the World volume. | The picture below shows the simulation World volume. A red electron beam enters the HRRL experimental cell from the left side and hits a 2 mm thick Tungsten target shown as the white vertical line inside the white inner box. The yellow box is a detector tracking cell. The roof is shown as 2 horizontal lines near the top of the World volume. | ||
− | [[Image:Run2_HRRL_ExptCell_Ceiling.jpg | 200 px]] | + | [[Image:Run2_HRRL_ExptCell_Ceiling.jpg |200 px]] <br> |
A few interesting events: | A few interesting events: | ||
− | [[Image:ElectronCreatesGammaOnHRRLExptCellCeiling.jpg | | + | [[Image:ElectronCreatesGammaOnHRRLExptCellCeiling.jpg|200px]] |
− | [[Image:GammaBouncesintoCeilinginHRRLExptCell.jpg | | + | [[Image:GammaBouncesintoCeilinginHRRLExptCell.jpg|200px]] |
+ | |||
+ | [[Image:GammaAbsorbtionTomographyHRRLExptCell.gif |200px|thumb|Figure GAT: Location of Gamma absoption in the HRRL experimental Cell]]<br> | ||
+ | Figure GAT shows the location of gamma absorption in the HRRL. There are 5 clear locations which see a lot of gammas. The two circular black disks located near the center of the experimental cell represent the windows of a virtual detector box used in the simulation. . The Tungsten foil appears in between these two circular disks. The two remaining locations which see a high gamma flux are on the walls of the HRRL experimental cell in the forward direction. The majority of the gammas directed to the ceiling appear to be absorbed at that location. The goal of this simulation is to estimate the radiation dose inside the HRRL experimental cell at the ceiling. I will divide the ceiling into square pixels having an area of 1 foot square in order to approximate a human standing on the ceiling at that location. I will then choose the pixel with the highest photon flux to estimate a dose. This pixel will most likely be directly above the beamline and near the end of the beam line in the cell. | ||
+ | |||
+ | |||
+ | === Ceiling Photon distribution=== | ||
=== Photon Energy -to- Dose === | === Photon Energy -to- Dose === | ||
+ | |||
+ | |||
+ | [[Image:DoseCalcFromEgamma.jpg | 400 px]] | ||
+ | |||
{| border="1" |cellpadding="20" cellspacing="0 | {| border="1" |cellpadding="20" cellspacing="0 | ||
|- | |- | ||
|Photon Energy || Dose Conversion Coeff | |Photon Energy || Dose Conversion Coeff | ||
|- | |- | ||
− | |(MeV) || | + | |(MeV) || rem <math>cm^2</math> s/ hr |
|- | |- | ||
|0.01 || 3.96E-6 | |0.01 || 3.96E-6 | ||
Line 170: | Line 278: | ||
|15.0 || 13.3E-6 | |15.0 || 13.3E-6 | ||
|} | |} | ||
+ | |||
== Concrete Definition and Stopping Power == | == Concrete Definition and Stopping Power == | ||
Line 221: | Line 330: | ||
Total | Total | ||
|- | |- | ||
− | |1.000E-02 1.804E+01 5.754E-03 1.805E+01 3.207E-04 1.710E-04 0.000E+00 | + | |1.000E-02 ||1.804E+01 ||5.754E-03 ||1.805E+01 ||3.207E-04 ||1.710E-04 ||0.000E+00 |
|- | |- | ||
− | |1.250E-02 1.526E+01 5.864E-03 1.526E+01 4.720E-04 2.072E-04 0.000E+00 | + | |1.250E-02 ||1.526E+01 ||5.864E-03 ||1.526E+01 ||4.720E-04 ||2.072E-04 ||0.000E+00 |
|- | |- | ||
− | |1.500E-02 1.330E+01 5.942E-03 1.330E+01 6.480E-04 2.419E-04 0.000E+00 | + | |1.500E-02 ||1.330E+01 ||5.942E-03 ||1.330E+01 ||6.480E-04 ||2.419E-04 ||0.000E+00 |
|- | |- | ||
− | |1.750E-02 1.184E+01 5.999E-03 1.184E+01 8.476E-04 2.755E-04 0.000E+00 | + | |1.750E-02 ||1.184E+01 ||5.999E-03 ||1.184E+01 ||8.476E-04 ||2.755E-04 ||0.000E+00 |
|- | |- | ||
|2.000E-02 1.070E+01 6.044E-03 1.071E+01 1.070E-03 3.080E-04 0.000E+00 | |2.000E-02 1.070E+01 6.044E-03 1.071E+01 1.070E-03 3.080E-04 0.000E+00 | ||
Line 386: | Line 495: | ||
− | [http:// | + | |
+ | [http://wiki.iac.isu.edu/index.php/HRRL Go Back] |
Latest revision as of 06:34, 5 February 2009
Dose Goal: 25 mRem/year to public (after ceiling assuming occupied 1/16 of the time) and 2 mrem/hr.
Mark Balzer: 282-5652
Brian Oborn: 282- 6243
This document describes the simulations performed to estimate the radiological background in the event that a 1 nA electron current from the HRRL enters the experimental cell.
Radiation monitors: Ludlum Model 45-8.
Low energy gamma cutoff = 60 keV
HRRL Running Conditions
8 mA
A 2" x 4" x 8 " Al brick was used as a FC by placing it at the exit port of the HRRL after a 90 degree magnet bends electrons towards the HRRL experimental Cell. The output of a FC after the 90 degree bend at a beam energy of 3 MeV, I= 8 mA, pulse width = 25 ns, and rep rate of 60 Hz is shown in the scope picture below.
An accelerator operator will be able to tune the beam at this setting.
Copper Simulation
A 10 m x 10m x 10m HURL experimental cells was simulated in which a 2 mm Copper target representing detectors was installed 1 m from the beam upstream wall and centered in the remaining dimensions of the room. The ceiling was set 3m above the copper target.
3 MeV
A comparison between MCNP-X and GEANT4: Both simulations threw
electrons onto a 2 mm thick Copper target located in the HRRL experimental Cell.Simulation | Gamma Energy deposited per | incident|||
Inside Cell | above 6" thick concrete Cell ceiling | Ion Chamber in HRRL Cell | Peak current limit at 25 ns and 1kHz | |
MCNPX | MeV (rad/C) | MeV (rad/C) | mA | |
GEANT4 | MeV (rad/C) | MeV (rad/C) |
Converting the energy from MeV to Joules
In terms of the energy per beam current charge we would have
(I assume a 100 kg person ( 1 rad = 1 J/100 kg) Units are not consistent. There is a mass unit missing in this conversion. Vakho)
Average Current for a 2mrad/hr dose limit
How can you get 56 pA from the HRRL?
Currently you can see an 8 mA current on a FC with a 25 nSecond pulse width.
Therefore: Restricting to HRRL to 2 mA peak currents with 25 nSec pulse widths and 1 Hz should keep the dose beyond a 6" concrete ceiling below 2 mrad/hr. 2 mA peak HRRL currents have been measured before using a FC from JLab.
- What running conditions will result in less than 25 mrad of dose for 2000 hours (1 year) of operation
- mA
The above predictions only considered gammas with energies above 100 keV. With the 100 keV cut removed I still see less than MeV (6770 MeV) of deposited energy per incident 3 MeV electrons.
7 MeV
Simulation | Gamma Energy deposited per | incident|||
Inside Cell | above 6" thick concrete Cell ceiling | Ion Chamber in HRRL Cell | Peak current limit at 25 ns and 1 kHz | |
MCNPX | MeV (rad/C) | MeV | mA | |
GEANT4 | MeV (rad/C) |
The GEANT4 histograms below are from 100 k Events not 1 Million like Vakhos.
Tungsten SImulation
I created a world volume filled with Air to represent the experimental cell.
I created a 2mm thick tungsten target that is 30 cm x 30 cm in area.
The image below shows several electrons hitting the tungsten foil, then scattering in air. The red lines are electrons and the green ones are photons.
Run 1
I then ran 1 million events in which an incident 7 MeV electron hit the 2 mm thick Tungsten with the physics processes
if (particleName == "gamma") { // gamma pmanager->AddDiscreteProcess(new G4PhotoElectricEffect); pmanager->AddDiscreteProcess(new G4ComptonScattering); pmanager->AddDiscreteProcess(new G4GammaConversion); } else if (particleName == "e-") { //electron pmanager->AddProcess(new G4MultipleScattering,-1, 1,1); pmanager->AddProcess(new G4eIonisation, -1, 2,2); pmanager->AddProcess(new G4eBremsstrahlung, -1, 3,3);
I only kept gamma which had a momentum component towards the ceiling (p_y>0).
The energy distribution (in MeV) of the gammas headed towards the ceiling is shown below. Of the 1 million electrons incident on the 2 mm thick Tungsten target, only 70,000 gammas were headed towards the cieling. This does not mean that they hit it, they could have hit the wall.
If I sum the above distribution I see a total energy of 43,987 MeV going up from the 1 million 7 MeV electrons hitting the 2mm Tungsten target.
1 Rad =
= the amount of energy absorbed per 100 kg of materialTo calculate the worst possible case lets assume all of the radiation is absorbed by a person (there is no concrete ceiling).
Converting the energy from MeV to Joules
In terms of the energy per beam current charge we would have
I we ran the HRRL for 1 hour at the maximum beam current of 80 mA per 100 ns pulse and 1 kHz rep rate then the dose to the ceiling would be
The total photon radiation hitting the upper half of the experimental cell is predicted to be 1.4 krad/hr. To determine the dose on a radiation detector you just need to scale by the solid angle.
Mark Balzer tells me that the ion chambers are cylinders of length 4 inches and 1 inch in diameter. The ion chamber's cylindrical axis is mounted parallel to the ceiling. We will be limited to running with beam current that generate 2 mRad/hr or less in a single ion chamber. As a first estimate I will treat the cylinder as having a rectangular surface area of 4 " x 1 " = 4 in^2 = 25.8 cm^2. The ion chamber is on the ceiling which is about 6 meters from the beam pipe. The solid angle is thus
- .
The predicted rate in an ion chamber would then be
- our max beam current for 1 mRad/hr would be = 5 mA peak
Or in terms of an average current
- average
Run 2: Ceiling Penetration
Setup
The picture below shows the simulation World volume. A red electron beam enters the HRRL experimental cell from the left side and hits a 2 mm thick Tungsten target shown as the white vertical line inside the white inner box. The yellow box is a detector tracking cell. The roof is shown as 2 horizontal lines near the top of the World volume.
A few interesting events:
Figure GAT shows the location of gamma absorption in the HRRL. There are 5 clear locations which see a lot of gammas. The two circular black disks located near the center of the experimental cell represent the windows of a virtual detector box used in the simulation. . The Tungsten foil appears in between these two circular disks. The two remaining locations which see a high gamma flux are on the walls of the HRRL experimental cell in the forward direction. The majority of the gammas directed to the ceiling appear to be absorbed at that location. The goal of this simulation is to estimate the radiation dose inside the HRRL experimental cell at the ceiling. I will divide the ceiling into square pixels having an area of 1 foot square in order to approximate a human standing on the ceiling at that location. I will then choose the pixel with the highest photon flux to estimate a dose. This pixel will most likely be directly above the beamline and near the end of the beam line in the cell.
Ceiling Photon distribution
Photon Energy -to- Dose
Photon Energy | Dose Conversion Coeff |
(MeV) | rem | s/ hr
0.01 | 3.96E-6 |
0.03 | 0.582E-6 |
0.05 | 0.290E-6 |
0.07 | 0.258E-6 |
0.1 | 0.283E-6 |
0.15 | 0.379E-6 |
0.2 | 0.501E-6 |
0.25 | 0.631E-6 |
0.3 | 0.759E-6 |
0.35 | 0.878E-6 |
0.4 | 0.985E-6 |
0.45 | 1.08E-6 |
0.5 | 1.17E-6 |
0.55 | 1.27E-6 |
0.6 | 1.36E-6 |
0.65 | 1.44E-6 |
0.7 | 1.52E-6 |
0.8 | 1.68E-6 |
1.0 | 1.98E-6 |
1.4 | 2.51E-6 |
1.8 | 2.99E-6 |
2.2 | 3.42E-6 |
2.6 | 3.82E-6 |
2.8 | 4.01E-6 |
3.25 | 4.41E-6 |
3.75 | 4.83E-6 |
4.25 | 5.23E-6 |
4.75 | 5.60E-6 |
5.0 | 5.80E-6 |
5.25 | 6.01E-6 |
5.75 | 6.37E-6 |
6.25 | 6.74E-6 |
6.75 | 7.11E-6 |
7.5 | 7.66E-6 |
9.0 | 8.77E-6 |
11.0 | 10.3E-6 |
13.0 | 11.8E-6 |
15.0 | 13.3E-6 |
Concrete Definition and Stopping Power
A 6 inch concrete floor is assumed to exist on the top of the experimental cell which will block radiation from penetrating to the offices above the cell.
Stopping power from NIST
Composition of CONCRETE, PORTLAND: Density (g/cm3) = 2.30000E+00 Mean Excitation Energy (eV) = 135.200000
COMPOSITION:
Atomic Number | Fraction by Weight |
1 | 0.010000 |
6 | 0.001000 |
8 | 0.529107 |
11 | 0.016000 |
12 | 0.002000 |
13 | 0.033872 |
14 | 0.337021 |
19 | 0.013000 |
20 | 0.044000 |
26 | 0.014000 |
(required)
Kinetic Energy(MeV) |
Stopping Power (MeV cm2/g) || CSDA Range(g/cm2) || RadiationYield || Density EffectParameter | |||||
Collision |
Radiative || Total | |||||
1.000E-02 | 1.804E+01 | 5.754E-03 | 1.805E+01 | 3.207E-04 | 1.710E-04 | 0.000E+00 |
1.250E-02 | 1.526E+01 | 5.864E-03 | 1.526E+01 | 4.720E-04 | 2.072E-04 | 0.000E+00 |
1.500E-02 | 1.330E+01 | 5.942E-03 | 1.330E+01 | 6.480E-04 | 2.419E-04 | 0.000E+00 |
1.750E-02 | 1.184E+01 | 5.999E-03 | 1.184E+01 | 8.476E-04 | 2.755E-04 | 0.000E+00 |
2.000E-02 1.070E+01 6.044E-03 1.071E+01 1.070E-03 3.080E-04 0.000E+00 | ||||||
2.500E-02 9.049E+00 6.107E-03 9.056E+00 1.580E-03 3.704E-04 0.000E+00 | ||||||
3.000E-02 7.899E+00 6.153E-03 7.905E+00 2.173E-03 4.298E-04 0.000E+00 | ||||||
3.500E-02 7.049E+00 6.189E-03 7.055E+00 2.844E-03 4.867E-04 0.000E+00 | ||||||
4.000E-02 6.393E+00 6.220E-03 6.400E+00 3.589E-03 5.415E-04 0.000E+00 | ||||||
4.500E-02 5.872E+00 6.249E-03 5.878E+00 4.405E-03 5.944E-04 0.000E+00 | ||||||
5.000E-02 5.446E+00 6.276E-03 5.453E+00 5.289E-03 6.457E-04 0.000E+00 | ||||||
5.500E-02 5.092E+00 6.302E-03 5.099E+00 6.238E-03 6.955E-04 0.000E+00 | ||||||
6.000E-02 4.793E+00 6.328E-03 4.799E+00 7.250E-03 7.440E-04 0.000E+00 | ||||||
7.000E-02 4.315E+00 6.381E-03 4.321E+00 9.450E-03 8.375E-04 0.000E+00 | ||||||
8.000E-02 3.948E+00 6.437E-03 3.955E+00 1.187E-02 9.269E-04 0.000E+00 | ||||||
9.000E-02 3.659E+00 6.497E-03 3.665E+00 1.450E-02 1.013E-03 0.000E+00 | ||||||
1.000E-01 3.425E+00 6.560E-03 3.431E+00 1.732E-02 1.096E-03 0.000E+00 | ||||||
1.250E-01 2.996E+00 6.733E-03 3.003E+00 2.514E-02 1.292E-03 0.000E+00 | ||||||
1.500E-01 2.706E+00 6.925E-03 2.713E+00 3.393E-02 1.477E-03 0.000E+00 | ||||||
1.750E-01 2.498E+00 7.134E-03 2.505E+00 4.353E-02 1.652E-03 0.000E+00 | ||||||
2.000E-01 2.341E+00 7.357E-03 2.349E+00 5.385E-02 1.819E-03 0.000E+00 | ||||||
2.500E-01 2.124E+00 7.843E-03 2.132E+00 7.627E-02 2.137E-03 0.000E+00 | ||||||
3.000E-01 1.982E+00 8.377E-03 1.990E+00 1.006E-01 2.438E-03 0.000E+00 | ||||||
3.500E-01 1.883E+00 8.952E-03 1.892E+00 1.264E-01 2.728E-03 8.781E-04 | ||||||
4.000E-01 1.811E+00 9.563E-03 1.820E+00 1.534E-01 3.011E-03 1.827E-02 | ||||||
4.500E-01 1.756E+00 1.021E-02 1.766E+00 1.813E-01 3.290E-03 3.821E-02 | ||||||
5.000E-01 1.714E+00 1.088E-02 1.725E+00 2.099E-01 3.565E-03 5.986E-02 | ||||||
5.500E-01 1.681E+00 1.159E-02 1.693E+00 2.392E-01 3.839E-03 8.276E-02 | ||||||
6.000E-01 1.655E+00 1.231E-02 1.668E+00 2.690E-01 4.112E-03 1.066E-01 | ||||||
7.000E-01 1.618E+00 1.383E-02 1.632E+00 3.296E-01 4.657E-03 1.562E-01 | ||||||
8.000E-01 1.593E+00 1.543E-02 1.609E+00 3.914E-01 5.204E-03 2.072E-01 | ||||||
9.000E-01 1.577E+00 1.709E-02 1.594E+00 4.539E-01 5.754E-03 2.587E-01 | ||||||
1.000E+00 1.566E+00 1.882E-02 1.585E+00 5.168E-01 6.308E-03 3.102E-01 | ||||||
1.250E+00 1.553E+00 2.339E-02 1.577E+00 6.751E-01 7.716E-03 4.363E-01 | ||||||
1.500E+00 1.551E+00 2.828E-02 1.580E+00 8.335E-01 9.157E-03 5.566E-01 | ||||||
1.750E+00 1.555E+00 3.342E-02 1.588E+00 9.914E-01 1.063E-02 6.704E-01 | ||||||
2.000E+00 1.560E+00 3.876E-02 1.599E+00 1.148E+00 1.213E-02 7.777E-01 | ||||||
2.500E+00 1.575E+00 4.998E-02 1.625E+00 1.459E+00 1.520E-02 9.746E-01 | ||||||
3.000E+00 1.590E+00 6.176E-02 1.651E+00 1.764E+00 1.835E-02 1.152E+00 | ||||||
3.500E+00 1.604E+00 7.400E-02 1.678E+00 2.064E+00 2.155E-02 1.312E+00 | ||||||
4.000E+00 1.617E+00 8.662E-02 1.704E+00 2.360E+00 2.479E-02 1.459E+00 | ||||||
4.500E+00 1.630E+00 9.956E-02 1.729E+00 2.651E+00 2.805E-02 1.595E+00 | ||||||
5.000E+00 1.641E+00 1.128E-01 1.754E+00 2.938E+00 3.134E-02 1.721E+00 | ||||||
5.500E+00 1.651E+00 1.263E-01 1.778E+00 3.221E+00 3.465E-02 1.839E+00 | ||||||
6.000E+00 1.661E+00 1.400E-01 1.801E+00 3.501E+00 3.796E-02 1.949E+00 | ||||||
7.000E+00 1.678E+00 1.680E-01 1.846E+00 4.049E+00 4.459E-02 2.152E+00 | ||||||
8.000E+00 1.693E+00 1.968E-01 1.890E+00 4.584E+00 5.122E-02 2.334E+00 | ||||||
9.000E+00 1.706E+00 2.261E-01 1.932E+00 5.108E+00 5.781E-02 2.500E+00 | ||||||
1.000E+01 1.718E+00 2.558E-01 1.973E+00 5.620E+00 6.437E-02 2.652E+00 | ||||||
1.250E+01 1.742E+00 3.320E-01 2.074E+00 6.855E+00 8.050E-02 2.984E+00 | ||||||
1.500E+01 1.761E+00 4.102E-01 2.171E+00 8.033E+00 9.619E-02 3.267E+00 | ||||||
1.750E+01 1.777E+00 4.899E-01 2.267E+00 9.160E+00 1.114E-01 3.513E+00 | ||||||
2.000E+01 1.791E+00 5.707E-01 2.362E+00 1.024E+01 1.261E-01 3.731E+00 | ||||||
2.500E+01 1.813E+00 7.350E-01 2.548E+00 1.228E+01 1.540E-01 4.106E+00 | ||||||
3.000E+01 1.831E+00 9.020E-01 2.733E+00 1.417E+01 1.799E-01 4.422E+00 | ||||||
3.500E+01 1.845E+00 1.071E+00 2.916E+00 1.594E+01 2.041E-01 4.694E+00 | ||||||
4.000E+01 1.857E+00 1.241E+00 3.099E+00 1.761E+01 2.266E-01 4.934E+00 | ||||||
4.500E+01 1.868E+00 1.413E+00 3.281E+00 1.917E+01 2.476E-01 5.148E+00 | ||||||
5.000E+01 1.877E+00 1.586E+00 3.463E+00 2.066E+01 2.673E-01 5.342E+00 | ||||||
5.500E+01 1.886E+00 1.760E+00 3.646E+00 2.206E+01 2.858E-01 5.519E+00 | ||||||
6.000E+01 1.893E+00 1.934E+00 3.828E+00 2.340E+01 3.032E-01 5.681E+00 | ||||||
7.000E+01 1.906E+00 2.286E+00 4.192E+00 2.590E+01 3.350E-01 5.971E+00 | ||||||
8.000E+01 1.918E+00 2.639E+00 4.557E+00 2.819E+01 3.634E-01 6.225E+00 | ||||||
9.000E+01 1.928E+00 2.994E+00 4.922E+00 3.030E+01 3.891E-01 6.451E+00 | ||||||
1.000E+02 1.936E+00 3.351E+00 5.288E+00 3.226E+01 4.123E-01 6.654E+00 | ||||||
1.250E+02 1.954E+00 4.248E+00 6.203E+00 3.662E+01 4.620E-01 7.087E+00 | ||||||
1.500E+02 1.969E+00 5.151E+00 7.120E+00 4.038E+01 5.025E-01 7.443E+00 | ||||||
1.750E+02 1.981E+00 6.059E+00 8.040E+00 4.368E+01 5.363E-01 7.746E+00 | ||||||
2.000E+02 1.992E+00 6.969E+00 8.961E+00 4.662E+01 5.650E-01 8.010E+00 | ||||||
2.500E+02 2.010E+00 8.797E+00 1.081E+01 5.170E+01 6.114E-01 8.451E+00 | ||||||
3.000E+02 2.024E+00 1.063E+01 1.266E+01 5.597E+01 6.474E-01 8.813E+00 | ||||||
3.500E+02 2.036E+00 1.247E+01 1.451E+01 5.965E+01 6.764E-01 9.119E+00 | ||||||
4.000E+02 2.046E+00 1.432E+01 1.636E+01 6.290E+01 7.003E-01 9.385E+00 | ||||||
4.500E+02 2.055E+00 1.616E+01 1.822E+01 6.579E+01 7.204E-01 9.620E+00 | ||||||
5.000E+02 2.064E+00 1.801E+01 2.008E+01 6.841E+01 7.376E-01 9.830E+00 | ||||||
5.500E+02 2.071E+00 1.986E+01 2.194E+01 7.079E+01 7.525E-01 1.002E+01 | ||||||
6.000E+02 2.078E+00 2.172E+01 2.379E+01 7.298E+01 7.656E-01 1.019E+01 | ||||||
7.000E+02 2.090E+00 2.543E+01 2.752E+01 7.688E+01 7.874E-01 1.050E+01 | ||||||
8.000E+02 2.100E+00 2.914E+01 3.124E+01 8.029E+01 8.051E-01 1.077E+01 | ||||||
9.000E+02 2.109E+00 3.286E+01 3.497E+01 8.331E+01 8.197E-01 1.100E+01 | ||||||
1.000E+03 2.117E+00 3.658E+01 3.870E+01 8.603E+01 8.320E-01 1.121E+01 |