=8/1/12=
 
=8/1/12=
  
Strung 35 Field wires on Sector 5 (now on SL2 - row 16).
+
Strung 28 Field wires on Sector 5 (now on SL2 - row 15).
  
 
Installed filters on Sector 6 chamber.
 
Installed filters on Sector 6 chamber.
 
  
 
=8/2/12=
 
=8/2/12=

Revision as of 22:47, 2 August 2012

8/1/12

Strung 28 Field wires on Sector 5 (now on SL2 - row 15).

Installed filters on Sector 6 chamber.

8/2/12

Strung 126 Field wires on Sector 5 (now on SL2 - row 33). Removed C1 pretensioner at row 25.

Strung 48 Sense wires on Sector 6 (now on SL2 - row 183).

Completed Tension Trend tests for both Sector 5 and 6 chambers.