=8/2/12=
 +
 +
Strung 126 Field wires on Sector 5 (now on SL2 - row 33). Removed C1 pretensioner at row 25.
 +
 +
Strung 48 Sense wires on Sector 6 (now on SL2 - row 183).
 +
 +
Completed Tension Trend tests for both Sector 5 and 6 chambers.

Revision as of 22:45, 2 August 2012

8/1/12

Strung 35 Field wires on Sector 5 (now on SL2 - row 16).

Installed filters on Sector 6 chamber.


8/2/12

Strung 126 Field wires on Sector 5 (now on SL2 - row 33). Removed C1 pretensioner at row 25.

Strung 48 Sense wires on Sector 6 (now on SL2 - row 183).

Completed Tension Trend tests for both Sector 5 and 6 chambers.