Difference between revisions of "201111 R1ProgressRep"
m (→11/3/11) |
m (→11/29/11) |
||
(23 intermediate revisions by the same user not shown) | |||
Line 22: | Line 22: | ||
All field wires are strung on SL2. | All field wires are strung on SL2. | ||
+ | |||
+ | [[file:20111104_Wires.png | 400 px]] | ||
[[file:20111104_Temp2.png | 400 px]] | [[file:20111104_Temp2.png | 400 px]] | ||
+ | |||
+ | ==11/7/11== | ||
+ | |||
+ | Spent the day visually inspecting for crossed wires. We should have the chamber rotated tomorrow and hopefully back to stringing later in the afternoon. | ||
+ | |||
+ | [[file:20111107_Temp1.png | 400 px]] | ||
+ | |||
+ | ==11/8/11== | ||
+ | |||
+ | Chamber was rotated this morning. | ||
+ | |||
+ | We started stringing SL1 mid-afternoon. We only managed 50 wires today. | ||
+ | |||
+ | [[file:20111108_Temp1.png | 400 px]] | ||
+ | |||
+ | Temperature drop was caused by our power supply overheating. For future reference, don't exceed the rated 60 Amps of current... | ||
+ | |||
+ | ==11/9/11== | ||
+ | |||
+ | I removed one of the covers for our large ducting in an attempt to get some air flow through the room (not the clean room). This appears to have changed the cyclic rate of our HVAC. Temperature min/max appears to have been unaffected. | ||
+ | |||
+ | [[file:20111109_Temp1.png | 400 px]] | ||
+ | |||
+ | The ducting cover will be put back in place tomorrow. | ||
+ | |||
+ | 63 wires were strung today. | ||
+ | |||
+ | [[file:20111109_Temp2.png | 400 px]] | ||
+ | |||
+ | ==11/10/11== | ||
+ | |||
+ | 63 wires were strung today. | ||
+ | |||
+ | Keeping the duct cover off until tomorrow. | ||
+ | |||
+ | ==11/11/11== | ||
+ | |||
+ | The duct cover was put back on about 1 PM. | ||
+ | |||
+ | [[file:20111111_Temp1.png | 400 px]] | ||
+ | |||
+ | 105 wires were strung today. | ||
+ | |||
+ | [[file:20111111_Temp2.png | 400 px]] | ||
+ | |||
+ | ==11/14/11== | ||
+ | |||
+ | 126 wires were strung today. | ||
+ | |||
+ | [[file:20111114_Temp1.png | 400 px]] | ||
+ | |||
+ | ==11/15/11== | ||
+ | |||
+ | 119 wires were strung today. We also changed our spool of field wire. | ||
+ | |||
+ | [[file:20111115_Temp1.png | 400 px]] | ||
+ | |||
+ | ==11/16/11== | ||
+ | |||
+ | 126 wires were strung today. | ||
+ | |||
+ | [[file:20111116_Temp1.png | 400 px]] | ||
+ | |||
+ | ==11/17/11== | ||
+ | |||
+ | 126 wires were strung today. We are at about the halfway point for SL1 (row 112). | ||
+ | |||
+ | [[file:20111117_Temp1.png | 400 px]] | ||
+ | |||
+ | ==11/18/11== | ||
+ | |||
+ | Took the girls shoe shopping this afternoon. Cleanroom shoes are on order now. | ||
+ | |||
+ | We still managed to do 126 wires today. | ||
+ | |||
+ | ==11/19/11== | ||
+ | |||
+ | I came in to do our weekly trend measurements. Power supply was not warm to the touch, so not sure what was going on with temperatures. | ||
+ | |||
+ | [[file:20111119_Temp1.png | 400 px]] | ||
+ | |||
+ | ==11/21/11== | ||
+ | |||
+ | 112 wires were strung today. | ||
+ | |||
+ | [[file:20111121_Temp1.png | 400 px]] | ||
+ | |||
+ | ==11/22/11== | ||
+ | |||
+ | 126 wires were strung today. | ||
+ | |||
+ | [[file:20111122_Temp1.png | 400 px]] | ||
+ | |||
+ | ==11/23/11== | ||
+ | |||
+ | I spent some time this afternoon testing and adjusting our HVAC temperature alarm. The alarm now goes off if temperatures exceed 72° F and if it falls below 68° F inside the cleanroom. | ||
+ | |||
+ | ==11/28/11== | ||
+ | |||
+ | 56 wires were strung today. | ||
+ | |||
+ | [[file:20111128_Temp1.png | 400 px]] | ||
+ | |||
+ | ==11/29/11== | ||
+ | |||
+ | 105 wires were strung today. | ||
+ | |||
+ | ==11/30/11== | ||
+ | |||
+ | 84 wires were strung today. | ||
+ | |||
+ | [[file:20111130_Temp1.png | 400 px]] |
Latest revision as of 22:52, 30 November 2011
11/1/11
70 wires were strung today. Our second stringer should be starting tomorrow.
11/2/11
91 wires were strung today.
11/3/11
The correct HVAC filters came in today. A clean filter was installed today at ~10 AM. A small rise in temperature can be seen in the temperature graph when this change was made.
77 wires were strung today.
11/4/11
91 wires were strung today.
All field wires are strung on SL2.
11/7/11
Spent the day visually inspecting for crossed wires. We should have the chamber rotated tomorrow and hopefully back to stringing later in the afternoon.
11/8/11
Chamber was rotated this morning.
We started stringing SL1 mid-afternoon. We only managed 50 wires today.
Temperature drop was caused by our power supply overheating. For future reference, don't exceed the rated 60 Amps of current...
11/9/11
I removed one of the covers for our large ducting in an attempt to get some air flow through the room (not the clean room). This appears to have changed the cyclic rate of our HVAC. Temperature min/max appears to have been unaffected.
The ducting cover will be put back in place tomorrow.
63 wires were strung today.
11/10/11
63 wires were strung today.
Keeping the duct cover off until tomorrow.
11/11/11
The duct cover was put back on about 1 PM.
105 wires were strung today.
11/14/11
126 wires were strung today.
11/15/11
119 wires were strung today. We also changed our spool of field wire.
11/16/11
126 wires were strung today.
11/17/11
126 wires were strung today. We are at about the halfway point for SL1 (row 112).
11/18/11
Took the girls shoe shopping this afternoon. Cleanroom shoes are on order now.
We still managed to do 126 wires today.
11/19/11
I came in to do our weekly trend measurements. Power supply was not warm to the touch, so not sure what was going on with temperatures.
11/21/11
112 wires were strung today.
11/22/11
126 wires were strung today.
11/23/11
I spent some time this afternoon testing and adjusting our HVAC temperature alarm. The alarm now goes off if temperatures exceed 72° F and if it falls below 68° F inside the cleanroom.
11/28/11
56 wires were strung today.
11/29/11
105 wires were strung today.
11/30/11
84 wires were strung today.