Line 3: | Line 3: | ||
| Completion Date || IAC ||Task | | Completion Date || IAC ||Task | ||
|- | |- | ||
− | |1/11? || | + | |1/11? || ||IAC engineers move HRRL to new location |
|- | |- | ||
− | | | + | |4/11/2011 || 2 weeks ($10 k) ||Built beam pipe and flanges (Kevin?) |
+ | |- | ||
+ | |4/18/2011 || 2 weeks ($10k) ||Chad builds and installs stands | ||
+ | |- | ||
+ | |1/11? || 2 weeks ($10k) ||IAC engineers install beam line with magnets | ||
+ | |- | ||
+ | |2/11? || ||Hunt Runs experiment | ||
+ | |- | ||
+ | |3/11? || ||Sadiq emittance measurements | ||
+ | |- | ||
+ | |3/11? || ||Sadiq and Khalid disassembles beam line for alignment | ||
|- | |- | ||
|3/30/11 || ||Order Gate Valve (4 week lead time) | |3/30/11 || ||Order Gate Valve (4 week lead time) | ||
|- | |- | ||
|4/4/11 || ||Complete Beam Line CAD drawing (J. Ellis) | |4/4/11 || ||Complete Beam Line CAD drawing (J. Ellis) | ||
− | |||
− | |||
− | |||
− | |||
|- | |- | ||
|7/2011 || 3 days ($1k) || Removed and reinstall Gun for alignment (Chad) | |7/2011 || 3 days ($1k) || Removed and reinstall Gun for alignment (Chad) |
Revision as of 15:41, 17 October 2011
Completion Date | IAC | Task |
1/11? | IAC engineers move HRRL to new location | |
4/11/2011 | 2 weeks ($10 k) | Built beam pipe and flanges (Kevin?) |
4/18/2011 | 2 weeks ($10k) | Chad builds and installs stands |
1/11? | 2 weeks ($10k) | IAC engineers install beam line with magnets |
2/11? | Hunt Runs experiment | |
3/11? | Sadiq emittance measurements | |
3/11? | Sadiq and Khalid disassembles beam line for alignment | |
3/30/11 | Order Gate Valve (4 week lead time) | |
4/4/11 | Complete Beam Line CAD drawing (J. Ellis) | |
7/2011 | 3 days ($1k) | Removed and reinstall Gun for alignment (Chad) |
8/2011 | Zero degree beam line aligned (Khalid, Sadiq) | |
1/25/2012 | Target Motor from Empire Magnetics | |
1/25/2012 | 1 week ($5k) | Target Chamber design (IAC engineer) |
1/25/2012 | Target Tungsten disks | |
2009-2012 | $30 k | 3 weeks of beam time |
IAC investment: $66k
Indirects from DOE :
IAC personnel salary paid : $80k
Although not requested, magnet power supplies and a LabView control interface were installed by Chad. We were planning on using the old blue power supplies from the airport.