Difference between revisions of "HRRL BeamLine 2011"
Jump to navigation
Jump to search
(One intermediate revision by one other user not shown) | |||
Line 9: | Line 9: | ||
|3/30/11 || Order Gate Valve (4 week lead time) | |3/30/11 || Order Gate Valve (4 week lead time) | ||
|- | |- | ||
− | |4/4/11 || Complete Beam Line CAD drawing | + | |4/4/11 || Complete Beam Line CAD drawing (J. Ellis) |
|- | |- | ||
|4/11/2011 || Built beam pipe and flanges (Kevin?) | |4/11/2011 || Built beam pipe and flanges (Kevin?) | ||
Line 17: | Line 17: | ||
|4/25/2011 || Built target chamber | |4/25/2011 || Built target chamber | ||
|} | |} | ||
− | |||
== Works to be done to put HRRL back == | == Works to be done to put HRRL back == | ||
Line 41: | Line 40: | ||
=== Break vacuum and put the parts together === | === Break vacuum and put the parts together === | ||
+ | 1. Put all the parts together and engineers will do it. | ||
− | + | == Works to be done to run HRRL == | |
1. Faraday cup wires to be soldered. | 1. Faraday cup wires to be soldered. | ||
Line 52: | Line 52: | ||
4. Positron target, chamber etc. | 4. Positron target, chamber etc. | ||
− | |||
− | |||
==Parts list== | ==Parts list== |
Latest revision as of 02:53, 17 October 2011
Beam Line installation 2011
Timeline
Completion Date | Task |
3/30/11 | Order Gate Valve (4 week lead time) |
4/4/11 | Complete Beam Line CAD drawing (J. Ellis) |
4/11/2011 | Built beam pipe and flanges (Kevin?) |
4/18/2011 | Complete Stands |
4/25/2011 | Built target chamber |
Works to be done to put HRRL back
A. 45 deg
1. Holder for 2nd Flag to be made.
2. Beam pipe for quad 7 to be made.
2. 45deg table to be drilled for holder.
3. Shopping at digikey for jaws.
90 deg
1. Extension pipe to be made. 2. Ion pump purchase 3. Test Jlab flag 4. Table for flag and detectors to be made 5. Annihilation target to be searched or reordered if not found.
Break vacuum and put the parts together
1. Put all the parts together and engineers will do it.
Works to be done to run HRRL
1. Faraday cup wires to be soldered.
2. Wires to be pulled from control area to the beamline.
3. Camera to be installed under 1st flag and calibrated.
4. Positron target, chamber etc.