(Created page with '{| border="1" |cellpadding="20" cellspacing="0 |- | Completion Date || Task |- |3/30/11 || Order Gate Valve (4 week lead time) |- |4/4/11 || Complete Beam Line CAD drawing |-…') |
|||
| Line 21: | Line 21: | ||
|1/25/2012 || Target Tungsten disks | |1/25/2012 || Target Tungsten disks | ||
|} | |} | ||
| + | |||
| + | [[Positrons#HRRL_beam_Line_installation]] | ||
Revision as of 21:35, 14 October 2011
| Completion Date | Task |
| 3/30/11 | Order Gate Valve (4 week lead time) |
| 4/4/11 | Complete Beam Line CAD drawing |
| 4/11/2011 | Built beam pipe and flanges (Kevin?) |
| 4/18/2011 | Chad builds X stands |
| 7/2011 | Removed Gun for alignment (Chad) |
| 8/2011 | Zero degree beam line aligned (Khalid, Sadiq) |
| 1/25/2012 | Target Motor from Empire Magnetics |
| 1/25/2012 | Target Chamber |
| 1/25/2012 | Target Tungsten disks |