(Created page with ' {| border="1" |cellpadding="20" cellspacing="0 |- |Mon || Tues || Wed || Thurs || Fri |- | 5/17/10 || 9/30/10 || 8/6/10 ||Sign MOU |- | 5/17/10 ||9/30/11 || 4/12/11 || Co…') |
(No difference)
|
Revision as of 21:10, 22 September 2011
Mon | Tues | Wed | Thurs | Fri |
5/17/10 | 9/30/10 | 8/6/10 | Sign MOU | |
5/17/10 | 9/30/11 | 4/12/11 | Contract recieved | |
8/3/2010 | 8/3/2010 | Readiness Review | ||
9/1/10 | 10/29/10 | Hire and train R1 Lead Stringer | ||
10/1/10 | 2/28/11 | Hire and train 2 R1 stringers | ||
11/16/09 | 11/30/10 | Build R1 Cleanroom | ||
11/5/2010 | 11/12/2011 | Ship 1st R1 Box From JLab to ISU | ||
12/17/2010 | 2/28/2011 | String First R1 Chambers | ||
2/21/2011 | 3/31/2011 | Ship remaining R1 Boxes From JLab to ISU | ||
7/13/12 | Complete 6th R1 chamber | |||
4/5/13 | 9/30/13 | Ship chambers, fixtures, platforms and crane to JLab |