− | [[File:FC Calibration 3.1.11.png | | + | Below is the FC calibration by using view screen observation for 44 MeV seup |
+ | |||
+ | [[File:FC Calibration 3.1.11.png | 1200 px]] | ||
Line 9: | Line 11: | ||
#red line is the fitting line for beam up | #red line is the fitting line for beam up | ||
#green line is the fitting line for beam down | #green line is the fitting line for beam down | ||
− | # | + | #black line is the fitting line for beam up and down |
We can see that all three line is almost the same so we can use the fitting line for whole range of kicker magnet which is | We can see that all three line is almost the same so we can use the fitting line for whole range of kicker magnet which is |
Latest revision as of 04:49, 4 March 2011
Below is the FC calibration by using view screen observation for 44 MeV seup
Here are:
- red line is the fitting line for beam up
- green line is the fitting line for beam down
- black line is the fitting line for beam up and down
We can see that all three line is almost the same so we can use the fitting line for whole range of kicker magnet which is