Difference between revisions of "PAS Thermalizing Box Design"
Jump to navigation
Jump to search
(18 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
− | =3D Models= | + | ='''3D Models'''= |
For all models: | For all models: | ||
Line 10: | Line 10: | ||
− | ==7/6/21== | + | =='''7/6/21'''== |
[[File:PAS_CH_Pb_tunnel_v13.png|300px|thumb|none|Render of top down view of preliminary experimental setup]] | [[File:PAS_CH_Pb_tunnel_v13.png|300px|thumb|none|Render of top down view of preliminary experimental setup]] | ||
Line 17: | Line 17: | ||
This design is preliminary and subject to change. No BorAl shielding has been included. | This design is preliminary and subject to change. No BorAl shielding has been included. | ||
− | = | + | =='''7/12/21'''== |
− | + | [[File:CH PAS Pb tunnel v21 Gd Converter.png|300px]] | |
− | + | [[File:CH PAS Pb Tunnel v21.png|300px]] | |
− | + | =='''7/14/21'''== | |
− | + | '''Poly Bricks for Setup''' | |
− | + | ==='''Poly Base'''=== | |
− | * | + | * 4X (4" x 2" x 6") |
− | |||
− | + | * 2X (4" x 2" x 7") | |
− | = | + | ==='''Poly Outside Wall'''=== |
− | * 4" x | + | * 1X (4" x 2" x 7") |
− | |||
− | + | * 1X (4" x 2" x 6") | |
− | + | * 2X (4" x 2" x 8") | |
+ | |||
+ | ==='''Poly Inside Wall'''=== | ||
+ | |||
+ | * 1X (4" x 2" x 3") | ||
+ | |||
+ | * 1X (4" x 2" x 8") | ||
+ | |||
+ | * 2X (4" x 2" x 6") | ||
+ | |||
+ | ===Poly Top=== | ||
+ | |||
+ | * 2X (4" x 2" x 7") | ||
+ | |||
+ | * 3X (4" x 2" x 6") | ||
+ | |||
+ | * 2X (2" x 2" x 6") | ||
+ | |||
+ | ='''Lead'''= | ||
+ | |||
+ | 50 lead bricks | ||
+ | |||
+ | * (49) 4" x 1" x 8" | ||
+ | |||
+ | * (1) 4" x 2" x 8" | ||
+ | |||
+ | ='''BorAl'''= | ||
+ | |||
+ | Needs to be calculated based off of new setup | ||
+ | |||
+ | ='''First Built Design'''= | ||
+ | |||
+ | |||
+ | |||
+ | {| class="wikitable" | ||
+ | |+ Feasibility setup exterior | ||
+ | |- | ||
+ | | [[File:PAS Feasibility 1.jpg|300px|thumb|center|Looking down the detector tunnel towards the converter]] || [[File:PAS Feasibility 2.jpg|300px|thumb|center|Overview of the setup with detector tunnel extending to the right and the source tunnel extending towards the back of the image]] | ||
+ | |- | ||
+ | | [[File:PAS Feasibility 3.jpg|300px|thumb|center|The backside of the source tunnel with regular poly exposed]] || [[File:PAS Feasibility 4.jpg|300px|thumb|center|Top view of the source tunnel with poly present as a stability measure for lead bricks stacked on end]] | ||
+ | |} | ||
+ | |||
+ | |||
+ | {| class="wikitable" | ||
+ | |+ Feasibility setup interior | ||
+ | |- | ||
+ | | [[File:Pb_tunnel_As_Built_7-19-2021.png|300px|thumb|center|Top down view of rendering of experimental setup]] || [[File:Pb_tunnel_As_Built_7-19-2021_2.png|300px|thumb|center|Interior walls removed to show poly and lead structures inside. Detector mounting hardware included to show rough position of detector in experimental setup]] | ||
+ | |} | ||
− | |||
− | |||
Latest revision as of 16:38, 19 July 2021
3D Models
For all models:
- Red - Lead brick
- White - Regular poly
- Green - Borated Poly
7/6/21
This design is preliminary and subject to change. No BorAl shielding has been included.
7/12/21
7/14/21
Poly Bricks for Setup
Poly Base
- 4X (4" x 2" x 6")
- 2X (4" x 2" x 7")
Poly Outside Wall
- 1X (4" x 2" x 7")
- 1X (4" x 2" x 6")
- 2X (4" x 2" x 8")
Poly Inside Wall
- 1X (4" x 2" x 3")
- 1X (4" x 2" x 8")
- 2X (4" x 2" x 6")
Poly Top
- 2X (4" x 2" x 7")
- 3X (4" x 2" x 6")
- 2X (2" x 2" x 6")
Lead
50 lead bricks
- (49) 4" x 1" x 8"
- (1) 4" x 2" x 8"
BorAl
Needs to be calculated based off of new setup
First Built Design