Difference between revisions of "PAS Experiment"

From New IAC Wiki
Jump to navigation Jump to search
Line 11: Line 11:
 
[[PAS_Experimental_Setup]]
 
[[PAS_Experimental_Setup]]
  
 +
[[PAS_HPGe_Detector]]
  
 
= DAQ =
 
= DAQ =

Revision as of 17:57, 4 June 2021

CH Task List

Materials

PAS_Shielding

NaI_Detectors

PAS_Experimental_Setup

PAS_HPGe_Detector

DAQ

6/1/21

  • ADC/TDC readout still not functioning. Dr. Forest is going to work on rebuilding the setup
  • I will attempt to hunt down manuals for each module and I will compile them here if found - need to look at Jeff Burggraf's wiki entries as this issue may already have a solution
  • Second nim bin causing errors with modules when bin is close to full. Could be drawing too much current, Dr. Dale is sourcing new nim bin from IAC to replace. We have extras here but need [math]\pm[/math]6V and all tested are either non-functioning or have [math]\pm[/math]12V & 24 but no 6V

Related Papers

See google drive for now




Contact me: Harpconn@isu.edu

User:Harpconn

UnderGraduate_Neutron_Correlations_Lab